File #: CM 24-298   
Type: Committee Memo Status: Referred
File created: 6/18/2024 In control: City Council
On agenda: 7/16/2024 Final action:
Title: Approve Final Contract with Award Construction and Accept Construction for the Wastewater Lift Stations 5, 6, 8, 11, and 15 Equipment Replacement Project
Attachments: 1. Agenda Memo, 2. Attachment A: Project Information Sheet, 3. Attachment B: Additional Project Information, 4. Attachment C: Wastewater Lift Station Program

TO: Committee of the Whole - Planning and Public Works

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Mike Haley

Senior Project Manager

Public Works

Jeff Thompson

Senior Engineer

Public Works

Steven Gibbs

Acting Capital Projects Division Manager

Public Works

Vangie Garcia

Deputy Public Works Director

 

 

TITLE:

title

Approve Final Contract with Award Construction and Accept Construction for the Wastewater Lift Stations 5, 6, 8, 11, and 15 Equipment Replacement Project

 

OVERVIEW STATEMENT:

recommendation

Public Works is requesting Council to approve the final contract and accept construction for the Wastewater Lift Stations 5, 6, 8, 11, and 15 Equipment Replacement project (No. 1518, 1519, 2108, 2109, 1204-404-03). This contract with Award Construction had a base bid amount of $4,495,713, plus change orders and bid items increases or decreases, resulting in a final contract amount of $4,431,264. The project upgraded aging equipment at five pump stations, increasing their life cycles.

 

This project completes the ten-station, six-year program to replace or rehabilitate city lift stations. The original cost estimate for the program was $44 million dollars with completion planned for 2025. The program was completed one year early at a cost of $39 million, resulting in $5 million in savings.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Community Strategic Plan - Objective #1:

Invest in infrastructure preservation and replacement across the city to maintain the current level of service, the reliability of capital assets, and provide timely and cost-effective replacement.

                     Required:

Council approval is required to accept a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

This project replaced aging wastewater lift station equipment and ensured continuation of service to the community.

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$4,431,264

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Healthy and Sustainable

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Wastewater CIP

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

N/A

Item has not been presented to Council

N/A

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

7/16/2024

Business Meeting

Approve

 

Time Constraints:

Following project acceptance, in accordance with RCW 60.28, the contract retainage will be released upon receipt of clearances from the Washington State Departments of Revenue and Labor and Industries, and a mandatory 45-day waiting period for filing claims and liens.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

The warranty period begins upon Council acceptance. Not accepting construction will result in delay of warranty start, increasing the project close-out cost.

 

 

ATTACHMENTS:

Attachment A: Wastewater Lift Station Project Information Sheet

Attachment B: Additional Project Information

Attachment C: Wastewater Lift Station Program