Title: Pool Improvement Project Update and Phase 2 Construction Contract
Attachments: 1. Agenda Memo, 2. Attachment A: Presentation
MEMO TO: Members of the City Council
FROM: Mayor Angela Birney
SUBJECT:
title
Pool Improvement Project Update and Phase 2 Construction Contract

I. RECOMMENDED ACTION
recommendation

Discuss the Pool Improvement Project and future Phase 2 construction contract.
body

I. DEPARTMENT CONTACTS

Carrie Hite Director of Parks and Recreation 425-556-2326
Rachel Van Winkle Deputy Director of Parks and Recreation 425-556-2334
Dave Tuchek Park Operations Manager 425-556-2318
John Mork Project Manager 425-556-2713
Bethany Kennedy Engagement Manager 425-556-2366

II. DESCRIPTION/BACKGROUND

The Redmond Pool is currently receiving an $8M renovation as approved in the 2019-2020 biennial budget. The purpose of the renovation is to improve essential and high priority systems and make structural improvements to allow the pool to operate an additional
25-30 years.

The Redmond Pool improvement project was identified in the Facilities Strategic Management Plan that was adopted by the City Council in January 2019. The City conducted extensive stakeholder involvement to gather input on the Future of Redmond's Community Centers and found aquatics facilities were ranked as the highest priority by the community.

The City Council adopted the 2019 - 2025 Capital Improvement Program (CIP) as part of the 2019-2020 overall budget. The CIP allocated $8M for the pool improvements in
2019-2020 timeframe.

Phase I - Essential System Improvements

McKinstry is under contract to complete approximately $5.4M in system repair and replacement that will improve overall pool facility energy efficiency and operation. The pool lining fix and UV filtration system brought this total to $5.9M. This work will result in lower utility use and costs along with improved building system performance and occupant experience. The following improvements are currently being performed.
* Boiler system
* Pool circulation system
* Pool heat exchanger
* Lighting
* Electrical service and panels
* ...