File #: AM No. 21-146   
Type: Consent Item Status: Passed
File created: 9/8/2021 In control: City Council
On agenda: 10/5/2021 Final action: 10/5/2021
Title: Approval of Consultant Agreement with BHC Consultants for Engineering Services for the Targeted Equipment Upgrades for Wastewater Lift Stations 5, 6, 8, 11 and 15 Projects in a Maximum Amount Payable of $758,000
Attachments: 1. Agenda Memo, 2. Attachment A: Description and Cost Estimate, 3. Attachment B: Revised 2021-2026 Capital Investment Lift Station Program Table, 4. Attachment C: Agreement, 5. Attachment D: Vicinity Map

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Dave Juarez

425-556-2733

 

DEPARTMENT STAFF:

Public Works

Mike Haley

Project Manager

Public Works

Steve Hitch

EUSD Engineering Supervisor

Public Works

Jon Spangler

Construction Division Manager

Public Works

Andy Rheaume

Interim EUSD Manager

 

 

TITLE:

title

Approval of Consultant Agreement with BHC Consultants for Engineering Services for the Targeted Equipment Upgrades for Wastewater Lift Stations 5, 6, 8, 11 and 15 Projects in a Maximum Amount Payable of $758,000

 

OVERVIEW STATEMENT:

recommendation

This consultant agreement will result in a design and bid documents for the Wastewater Lift Stations 5, 6, 8, 11 and 15 projects targeted equipment upgrades.   The BHC agreement is shown in Attachment C.  The design scope of work will be focused on extending the life of these five lift stations.  This effort will allow for smaller investments in lift station improvements to ensure that the stations can operate with limited risk of failure for a longer period before full replacement. The targeted equipment upgrades are scheduled to be complete in late 2022 and early 2023.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

N/A

                     Required:

Council approval is required for funding

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

This design work will produce bid documents for the project that will replace equipment at five (5) Wastewater Lift Stations.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

The proposed action is to fund the design for five (5) Wastewater Lift Station Targeted Equipment Upgrade Projects. The proposed project description and cost estimate is shown in Attachment A.  The revised CIP funding is shown in the table in Attachment B.

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

Capital Improvement Program Map Number ID48, ID49, EH183, SE50 and WL47

 

Budget Priority:

Healthy and Sustainable

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Wastewater CIP

 

Budget/Funding Constraints:

The 2021-2022 Capital Investment

 

  Additional budget details attached

 

 

 

 

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

7/14/2021

Committee of the Whole - Planning and Public Works

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

N/A

 

 

ANTICIPATED RESULT IF NOT APPROVED:

If not approved, the current program to fully replace the lift stations would continue. However, since funding is not adequate to support replacement of the lift stations identified in the 2021- 2022 CIP, projects would need to be pushed out in time until funds can be accumulated to cover the replacement costs.  Equipment upgrades will be necessary to ensure continued operations and reliability of the Lift Stations, as delay in replacing the Lift Station Equipment will put them at risk of failure.

 

 

ATTACHMENTS:

Attachment A: Description and Cost Estimate

Attachment B: Revised 2021-2026 Capital Investment Lift Station Program Table

Attachment C: Consultant Agreement

Attachment D: Vicinity Map