Legislation Details

File #: CM 25-605   
Type: Committee Memo Status: Agenda Ready for Committee of the Whole
File created: 10/6/2025 In control: Committee of the Whole - Planning and Public Works
On agenda: 11/3/2025 Final action:
Title: Resolution to Establish Additional Sewer Connection Charges for Redmond Town Center Area Sewer Improvements
Attachments: 1. Attachment A: Vicinity Map, 2. Attachment B: BHC Technical Memorandum, 3. Attachment C: Draft Resolution
TO: Committee of the Whole - Planning and Public Works
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786

DEPARTMENT STAFF:
Public Works
Jeff Thompson
Senior Utility Engineer
Public Works
Chris Stenger
Deputy Public Works Director


TITLE:
title
Resolution to Establish Additional Sewer Connection Charges for Redmond Town Center Area Sewer Improvements


OVERVIEW STATEMENT:
recommendation
Public Works is requesting Council approval of a Resolution to establish Additional Sewer Connection Charges (ACCs) for properties within the Redmond Town Center area. These charges will enable the City to recover costs associated with sewer infrastructure improvements required to support anticipated growth outlined in the Redmond 2050 Comprehensive Plan.


To accommodate this growth, the City will undertake critical sewer system upgrades, including the upsizing of Lift Station #17 and associated sewer mains. While these improvements were identified as "Developer-Funded" in the 2024 General Sewer Plan, the City is proactively funding the work to help remove redevelopment barriers in the area. ACCs will ensure equitable cost recovery from parcels that directly benefit from these upgrades.


The total estimated project cost is $20.8 million. Charges will be assessed at the parcel level based on parcel size and the proportional benefit received. The proposed Resolution also includes provisions for cost reconciliation: property owners will receive refunds if actual project costs are lower than estimated; however, no additional charges will be imposed if actual costs exceed projections.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
2050 Comprehensive Plan & General Sewer Plan

o UT-1: Ensure that adequate public utilities and facilities are planned for, located, extended, and sized...

Click here for full text