Legislation Details

File #: CM 26-571   
Type: Committee Memo Status: Agenda Ready for Committee of the Whole
File created: 9/9/2026 In control: Committee of the Whole - Parks and Environmental Sustainability
On agenda: 9/22/2026 Final action:
Title: Approve Consultant Services Agreement Supplement 1 with Progressive Design Build Consulting LLC for the Teen Center Project
Attachments: 1. Agenda Memo, 2. Attachment A: Project Information Sheet, 3. Attachment B: Consultant Agreement Supplement 1
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Committee of the Whole - Parks and Environmental Sustainability

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Parks

Loreen Hamilton

425-556-2336

Public Works

Chris Stenger (Interim Director)

425-403-5510

 

 

DEPARTMENT STAFF:

Public Works

Shailee Jain

Project Manager

Public Works

Eric Dawson

Engineering Supervisor

Public Works

Steve Gibbs

Capital Division Manager

Parks

Danika Globokar

Deputy Parks Director

 

TITLE:

title

Approve Consultant Services Agreement Supplement 1 with Progressive Design Build Consulting LLC for the Teen Center Project

recommendation

 

 

OVERVIEW STATEMENT:

Parks and Public Works are requesting to approve the consultant services agreement supplement with Progressive Design Build Consulting LLC (PDBC) in the amount of $268,958. This supplement is for owner’s advisory services for the Teen Center project, Project No. 2571. It increases the maximum amount payable to $317,808.

 

An original contract in the amount of $48,850 was awarded to PDBC to provide owner’s representative services and support the City’s application to the state’s Project Review Committee for approval to use an alternative delivery method for the project. The contract also allowed PDBC to begin supporting the procurement of a design-build team to help expedite the project in accordance with Council direction. The original contract was not brought to Council for approval because it was below the $50,000 threshold.

body

 

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Parks, Arts, Recreation, Culture, and Conservation Plan (PARCC); Teen Services Engagement Report (2025); Community Priorities for the Future of Redmond’s Community Centers (2017)

                     Required:

o                     Council approval is required to award an architectural and engineering services agreement that exceeds $50,000 (2018 City Resolution 1503).

o                     Council Action AM No 25-184: “Approval to Rebuild the Teen Center on the Same Location. Prioritize Expedience in Construction, Centering Teen Voices in the Design Process, and Including Music Performance Space and a Dedicated Recording Studio to Continue the Old Firehouse Teen Center Legacy”

                     Council Request:

N/A

                     Other Key Facts:

Parks and Public Works are requesting this item go forward for Council approval at the October 6, 2026, Council business meeting.

 

 

OUTCOMES:

Approving this action keeps the City on the path to implementation of the Teen Center project.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

Community engagement will be a key part of the project moving forward. Engagement will be discussed in monthly project updates to Council.

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$268,958

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

The budget shown in the project information sheet aligns with what is in the proposed 2027-2032 CIP

 

Budget Offer Number:

545

 

Budget Priority:

Healthy and Sustainable

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Bond Proceeds, General Fund, Grant (potential regional partners), Impact Fees, General Govt/Facilities CIP, Real Estate Excise Tax, pending approval of the 2027-2032 CIP

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

N/A

Item has not been presented to Council

N/A

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

10/6/2026

Business Meeting

Approve

 

Time Constraints:

N/A

 

ANTICIPATED RESULT IF NOT APPROVED:

This contract is needed to continue receiving owners advisory support services for procurement of the design-build team and implementing the validation phase of implementation for the Teen Center Project. This is in line with council direction that this project should be expedited. Not approving the contract could delay DB procurement process and potentially Teen Center construction.

 

 

ATTACHMENTS:

Attachment A: Teen Center Project Information Sheet

Attachment B: Consultant Agreement Supplement 1