File #: AM No. 25-A364 PW   
Type: Consent Item Status: Agenda Ready
File created: 10/27/2025 In control: City Council
On agenda: 11/18/2025 Final action:
Title: Award of the Construction Contract with Earthworks Solutions, LLC of Auburn WA and Approve Consultant Services Agreement Supplement 1 with Consor, Inc. for the Pavement Management - NE 24th Street (West Lake Sammamish Parkway to 172nd Avenue NE) Project
Attachments: 1. Attachment A: Project Information Sheet, 2. Attachment B: Additional Project Information, 3. Attachment C: Consor Supplemental Agreement 01

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Mike Haley

Project Manager

Public Works

Steve Gibbs

Capital Projects Division Manager

Public Works

Vangie Garcia

Deputy Public Works Director

 

 

TITLE:

title

Award of the Construction Contract with Earthworks Solutions, LLC of Auburn WA and Approve Consultant Services Agreement Supplement 1 with Consor, Inc. for the Pavement Management - NE 24th Street (West Lake Sammamish Parkway to 172nd Avenue NE) Project

 

OVERVIEW STATEMENT:

recommendation

This project will rehabilitate the NE 24th Street corridor from West Lake Sammamish Parkway to 172nd Avenue NE by replacing aging water, sewer, and stormwater infrastructure that has reached the end of its useful life and extending the pavement life through asphalt overlay and channelization improvements. Completing the utility upgrades in advance of the resurfacing work minimizes future roadway disruptions and protects the City’s investment.

 

Public Works requests Council approval to award the construction contract to Earthworks Solutions, LLC as the lowest responsible bidder, in the amount of $6,307,345 for the Pavement Management - NE 24th Street (West Lake Sammamish Parkway to 172nd Avenue NE) Project (Project No. 2319). Public Works also requests Council approval of Supplemental Agreement No. 1 to the consultant services contract with Consor, Inc., in the amount of $380,710, for construction engineering and inspection support services. The supplemental agreement would increase the maximum amount payable for consultant services to $1,774,670.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Transportation Master Plan

Community Strategic Plan - Objective #1: Invest in infrastructure preservation and replacement across the city to maintain the current level of service, the reliability of capital assets, and provide timely and cost-effective replacement

                     Required:

Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

NE 24th Street is a key east-west corridor for Redmond. Approving this contract and consultant supplement will allow replacement of the existing water, sewer, and stormwater pipes, rehabilitation of the pavement surface, upgrades to ADA-compliant curb ramps, updated street lighting, and installation of new roadway and bike markings. Additional work includes coordination with King County Metro to improve bus stops along the corridor.

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$6,307,345 Construction Contract

$380,710 Supplemental Agreement Number 1

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Transportation, Water, Wastewater, and Stormwater CIPs; Transportation Benefit District

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

11/3/2025

Committee of the Whole - Planning and Public Works

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

N/A

N/A

 

Time Constraints:

Award of bid must occur within 60 days of the bid opening (which occurred on September 25, 2025) or the contractor may withdraw their bid.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Not approving contract will result in delaying construction, increasing the cost to complete the project.

 

 