File #: AM No. 22-062   
Type: Consent Item Status: Passed
File created: 4/6/2022 In control: City Council
On agenda: 4/19/2022 Final action: 4/19/2022
Title: Approval of the Overlake Village Light Rail Station Operations and Maintenance Agreement .
Attachments: 1. Agenda Memo, 2. Attachment A: O&M Agreement, 3. Attachment B: O&M Agreement General Maintenance Limits, 4. Attachment C: Pedestrian Bridge Artwork Maintenance Information, 5. Attachment D: Artist Agreement

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Planning and Community Development

Carol V. Helland

425-556-2107

Public Works

Phil Williams

425-556-2880

 

DEPARTMENT STAFF:

Planning and Community Development

Vangie Garcia

Manager, Transportation Planning & Engineering

Planning and Community Development

Peter Dane

Principal Planner

 

 

TITLE:

title

Approval of the Overlake Village Light Rail Station Operations and Maintenance Agreement

.

 

OVERVIEW STATEMENT:

recommendation

The Operations and Maintenance Agreement enables construction completion and documents the roles and responsibilities required for future operation and maintenance between Redmond and Sound Transit at the Station site.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Transportation Master Plan

                     Required:

None

                     Council Request:

N/A

                     Other Key Facts:

Sound Transit and Redmond have overlapping infrastructure on the Station site. This agreement is critical and necessary as assets are opened to the public. 

 

 

 

 

OUTCOMES:

Redmond and Sound Transit will agree upon operation and maintenance responsibilities for the future Overlake Village Light Rail Station assets. This agreement is required to be in place for:

-                     Redmond to take ownership of City assets currently under construction including the Overlake Village Station Pedestrian Bicycle Bridge and artwork, the Overlake Village Stormwater Infiltration Vault, and DaVinci Avenue

-                     Sound Transit to complete construction, operate, and maintain Station elements that overlap with the DaVinci Avenue right of way

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

2018-Present

                     Outreach Methods and Results:

Staff from each public works functional area and transportation maintenance and engineering were involved in reviewing the Overlake Village Station Operations and Maintenance Agreement. The Transit Way Agreement enables components of the Operations and Maintenance Agreement to be implemented and therefore relied on the Overlake Village Station Operations and Maintenance Agreement process for staff outreach.  

                     Feedback Summary:

City staff would prefer not to utilize the Sound Transit track access process which adds Sound Transit permitting requirements for City maintenance of City assets on Sound Transit property. However, staff recognize the requirements are placed on Sound Transit by federal railroad rules and that the City assets, such as the Overlake Village Pedestrian Bicycle Bridge, are important and worth maintaining even with the additional requirements.

 

 

BUDGET IMPACT:

 

Total Cost:

Owning and maintaining City assets at the Overlake Village Station site, such as the Overlake Village Pedestrian Bridge and DaVinci Avenue, will have maintenance costs. Details will be included in upcoming budget requests.

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP - Overlake Urban Center Investments (Map # 13)

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

 

Funding source(s):

CIP

 

Budget/Funding Constraints:

None

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

8/19/2014

Business Meeting

Approve

4/5/2022

Committee of the Whole - Planning and Public Works

Receive Information

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

The Operations and Maintenance Agreement must be approved prior to:

-                     The City taking ownership of City assets and opening them to the public; and

-                     Sound Transit opening the portion of the site that overlaps with DaVinci Avenue right of way.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

City assets and a portion of Sound Transit’s Station will not be opened to the public.

 

 

ATTACHMENTS:

Attachment A: Overlake Village Station Operation and Maintenance Agreement

Attachment B: Overlake Station - Operations & Maintenance Agreement General Maintenance Limits

Attachment C: Pedestrian Bridge Artwork Maintenance Information

Attachment D: Artist Agreement Assignment