title
Approval of Consultant Services Supplement 3 with Opsis Architecture, LLP, in the Amount of $325,000, for a Total Contract Budget of $5,536,638, for the Redmond Senior and Community Center Project
OVERVIEW STATEMENT:
recommendation
The architect consultant team has incurred additional costs over what was estimated for Contract Supplement 2 (Construction Administration) due to extended construction duration and higher than estimated number of construction submittals. The recent budget adjustment approved by Council on February 20, 2024 included funding for the supplement.
body
☒ Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
☐ Receive Information ☐ Provide Direction ☒ Approve
REQUEST RATIONALE:
• Relevant Plans/Policies:
o Envision Redmond Senior Center Building Stakeholders Report March 2020
o Redmond Community Strategic Plan
o 2017 Community Priorities for the Future of Redmond’s Community Centers Report
o Redmond Comprehensive Plan
o Redmond Parks, Arts, Recreation, Culture, and Conservation (PARCC) Plan
o Redmond Facilities Strategic Management Plan
o 2017-2022 Redmond Capital Investment Program (CIP). Redmond Zoning Code 21.10.070B
• Required:
Council approval is required to award an architectural and engineering services agreement that exceeds $50,000 (2018 City Resolution 1503)
• Council Request:
N/A
• Other Key Facts:
The current approved $61,700,000 budget includes funding for this consultant supplement.
OUTCOMES:
Approval of the budget supplement would allow completion of the senior and community center and keep the project on track for a grand opening in the spring of 2024.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
• Timeline (previous or planned):
See Attachment B - Additional Project Information
• Outreach Methods and Results:
See Attachment B - Additional Project Information
• Feedback Summary:
See Attachment B - Additional Project Information
BUDGET IMPACT:
Total Cost:
Current Budget: $5,261,638
Proposed Supplement: $325,000
Proposed Budget: $5,536,638
Approved in current biennial budget: ☒ Yes ☐ No ☐ N/A
Budget Offer Number:
CIP
Budget Priority:
Infrastructure, Healthy and Sustainable, Vibrant and Connected
Other budget impacts or additional costs: ☒ Yes ☐ No ☐ N/A
If yes, explain:
Note that the proposed consultant supplement is included in the current $61,700,000 budget approved by Council on February 20, 2024.
Funding source(s):
Debt proceeds |
$ 16,139,840 |
General Fund |
$ 13,236,527 |
Grants |
$ 1,725,000 |
Impact Fees |
$ 14,493,065 |
Misc - Solar Panels + contributions from Amazon and Emerald Heights |
$ 305,457 |
REET |
$ 15,800,111 |
Total Approved Budget |
$ 61,700,000 |
Budget/Funding Constraints:
The City Council approved a total project budget of $61,700,000 on February 20, 2024. Councilmanic Bonds were issued with City Council approval in May 2022.
☒ Additional budget details attached
COUNCIL REVIEW:
Previous Contact(s)
Date |
Meeting |
Requested Action |
N/A |
See Attachment B: Additional Project Information |
N/A |
Proposed Upcoming Contact(s)
Date |
Meeting |
Requested Action |
N/A |
None proposed at this time |
N/A |
Time Constraints:
N/A
ANTICIPATED RESULT IF NOT APPROVED:
If the budget supplement is not approved, construction administration will continue, but a reduced level to meet the current budget. Reduced construction administration could result in reduced quality of construction.
ATTACHMENTS: