Skip to main content
City of Redmond Logo
File #: AM No. 25-008   
Type: Consent Item Status: Passed
File created: 1/3/2025 In control: City Council
On agenda: 1/21/2025 Final action: 1/21/2025
Title: Approval of a Contract for the SQL Server Database Administration Managed Services
Attachments: 1. Agenda Memo, 2. Attachment A: Contract

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Technology and Information Services

Michael Marchand

425-556-2929

 

DEPARTMENT STAFF:

Technology and Information Services

Melissa Brady

Enterprise Data and GIS Manager

 

 

TITLE:

title

Approval of a Contract for the SQL Server Database Administration Managed Services

 

OVERVIEW STATEMENT:

recommendation

The City currently uses a managed services contract to manage and administer our SQL Server Database environment.  We have been using the current vendor for 8 years to augment our internal staff that don’t have the capacity to manage this system.   Our current contract expired in October 2024 and we are asking Council to approve another 2 year contract.   In addition, we are asking this to be sole source since we have an established relationship with the current vendor and they are experts on our database architecture and the associated databases.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

N/A

                     Required:

N/A

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

This managed services contract keeps our SQL Server Database environment up to date and safe and secure.   This environment supports our enterprise business systems such as D365, Eden, Springbrook, Lucity, and EnerGOV.

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$71K/Year for two years

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

2025-2026 Budget Offer 0000294

 

Budget Priority:

Strategic and Responsive

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

General Fund

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

1/14/2025

Committee of the Whole - Finance, Administration, and Communications

Receive Information

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

 

Time Constraints:

Existing Contract expired October 2024 and we are currently using the vendor on a month to month basis until we can get a new contract approved.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

If we were unable to procure SQL Server Database Administration Managed Services, we would have to convert an existing FTE to a database administrator requiring us to pull staff off other projects and priorities delaying projects such as CIP Project Management, UKG HR/Payroll.

 

 

ATTACHMENTS:

Attachment A: Contract