File #: AM No. 25-A373 PW   
Type: Consent Item Status: Agenda Ready
File created: 10/8/2025 In control: City Council
On agenda: 11/18/2025 Final action:
Title: Approval of the Final Contract with Active Construction Incorporated in the Amount of $3,383,138, and Acceptance of Construction for the 156th Cycle Track Project
Attachments: 1. Attachment A: Project Information Sheet, 2. Attachment B: Additional Project Information

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Aaron Noble

Project Manger

Planning and Community Development

Micah Ross

Functional Area Lead

Public Works

Steve Gibbs

Division Manager

Public Works

Vangie Garcia

Deputy Public Works Director

 

 

TITLE:

title

Approval of the Final Contract with Active Construction Incorporated in the Amount of $3,383,138, and Acceptance of Construction for the 156th Cycle Track Project

 

OVERVIEW STATEMENT:

recommendation

Public Works is requesting Council to approve the final contract and accept construction for the 156th Cycle Track project (No. 2001). This contract with Active Construction Incorporated had a base bid amount of $3,259,259, plus or minus change orders and bid items increases or decreases, resulting in a final contract amount of $3,382,138.54

 

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Capital Investment Program

                     Required:

Council approval is required to accept a Public Works contract that exceeds $300,000 (2018 City Resolution 1503

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

This project built a modally separated pedestrian walkway and bicycle track along 156th Ave NE from NE 28th St to NE 31st St and NE 36th St to NE 40th St. The cycle track extends the portion built by Microsoft and improves safety for pedestrians and cyclists along this busy arterial. The project met the objectives.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$3,382,138.54

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Transportation CIP, Grant

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

5/18/2021

Business Meeting

Approve

6/20/2023

Business Meeting

Approve

7/5/2025

Business Meeting

Approve

11/3/2025

Committee of the Whole - Planning and Public Works

Approve

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

Following project acceptance, in accordance with RCW 60.28, the contract retainage will be released upon receipt of clearances from the Washington State Departments of Revenue and Labor and Industries, and a mandatory 45-day waiting period for filing claims and liens.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

The warranty period begins upon Council acceptance. Not accepting construction will result in delay of warranty start, increasing the project close-out cost.

 

 

ATTACHMENTS:

Attachment A: 156th Cycle Track Project Information Sheet

Attachment B: Additional Project Information