Title: Approval of Consultant Services Agreement Supplement 1 with Perteet Engineering, in the Amount of $110,384, for the Avondale Road Preservation Project
Attachments: 1. Agenda Memo, 2. Attachment A: Project Information Sheet, 3. Attachment B: Additional Project Information (Perteet Supplement), 4. Attachment C: Supplemental Agreement 1

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Joseph O’Leary

Senior Project Manager

 

 

TITLE:

title

Approval of Consultant Services Agreement Supplement 1 with Perteet Engineering, in the Amount of $110,384, for the Avondale Road Preservation Project

 

OVERVIEW STATEMENT:

recommendation

This consultant services agreement supplement with Perteet Engineering in the amount of $110,384 is for construction services for the Avondale Road Preservation project, Project No. 2120-096-02 (20012120). It increases the maximum amount payable to $461,481.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

N/A

                     Required:

Council approval is required to award an Architectural and Engineering Services agreement that exceeds $50,000 (2018 City Resolution 1503)

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

Approving this action keeps the City on a path to completing the construction operation safely and will improve reliability for the driving public and bicycles for years to come. The project will repave approximately 2,240 feet of Avondale Road, improving safety in the corridor. In addition, curb ramps within the project limits will be brought up to current ADA standards. Existing bike lanes will be expanded to provide buffered bike lanes, increasing safety for bikers.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$110,384

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

General Fund, Real Estate Excise Tax, Federal Grant, Business Tax

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

8/2/2023

Committee of the Whole - Planning and Public Works

Approve

 

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

The supplement needs to be approved prior to beginning construction to allow the consultant to provide the required services.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Construction Engineering support is required for the project to be built. If the proposal is not approved, it could lead to delays and increased costs.

 

 

ATTACHMENTS:

Attachment A - Project Information Sheet

Attachment B - Additional Project Information