TO: Committee of the Whole - Public Safety and Human Services
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
|
Parks |
Loreen Hamilton |
425-556-2336 |
|
Public Works |
Chris Stenger |
425-403-5510 |
DEPARTMENT STAFF:
|
Public Works |
Shailee Jain |
Senior Engineer |
|
Public Works |
Eric Dawson |
Capital Supervisor |
|
Public Works |
Steve Gibbs |
Capital Division Manager |
|
Parks |
Danika Globokar |
Deputy Parks Director |
TITLE:
title
Teen Center Project Update
OVERVIEW STATEMENT:
recommendation
Parks and Public Works are providing an informational monthly update on the Teen Center Project.
Summary provided below:
- Design-Builder Procurement: Design-builder contract through the Validation phase provided to Council for direction on November 17, 2026, as a separate agenda item.
- Initial Visioning & Community Engagement: Initial visioning is underway. Feedback is being compiled to inform the Design-Builder’s future community engagement and design process. Initial feedback included the following themes:
o Music is vital; but diversity of spaces was emphasized from teens including safe and inclusive spaces, quiet study spaces, gathering spaces for a variety of interests, and outdoor spaces.
o Welcoming teen centered spaces that is easy to reach on public transportation, biking, or walking.
o Center teen voices and rebuild trust as we move into the future.
- Upcoming Work (November-December 2026): Planned activities include elected official engagement, consolidating initial visioning results, geotechnical desktop analysis, and-pending contract approval-development of the engagement roadmap and validation schedule, review of existing project information, and beginning subconsultant procurement.
- Staff plan to introduce Council to the Design-Builder team and Owner’s Representative in early 2027.
body
☒ Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
☒ Receive Information ☐ Provide Direction ☐ Approve
REQUEST RATIONALE:
• Relevant Plans/Policies:
Parks, Arts, Recreation, Culture, and Conservation Plan (PARCC)
Teen Services Engagement Report (2025)
Community Priorities for the Future of Redmond’s Community Centers (2017)
• Required:
Council Action AM No 25-184
• Council Request:
N/A
• Other Key Facts:
N/A
OUTCOMES:
We are taking steps towards implementing the Teen Center Project in accordance with Council Action AM No 25-184:
“Approval to Rebuild the Teen Center on the Same Location. Prioritize Expedience in Construction, Centering Teen Voices in the Design Process, and Including Music Performance Space and a Dedicated Recording Studio to Continue the Old Firehouse Teen Center Legacy”
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
• Timeline (previous or planned):
Community engagement will be a key component of the project moving forward. An engagement plan will be developed in collaboration with the Design-Build team. Initial visioning efforts are already underway.
Additional details are provided in Attachment A.
• Outreach Methods and Results:
N/A
• Feedback Summary:
N/A
BUDGET IMPACT:
Total Cost:
N/A
Approved in current biennial budget: ☐ Yes ☒ No ☐ N/A
Budget Offer Number:
545
Budget Priority:
Healthy & Sustainable
Other budget impacts or additional costs: ☐ Yes ☐ No ☒ N/A
If yes, explain:
N/A
Funding source(s):
N/A
Budget/Funding Constraints:
N/A
☐ Additional budget details attached
COUNCIL REVIEW:
Previous Contact(s)
|
Date |
Meeting |
Requested Action |
|
5/5/2026 |
Committee of the Whole - Planning and Public Works |
Receive Information |
|
7/28/2026 |
Committee of the Whole - Parks and Environmental Sustainability |
Receive Information |
|
9/22/2026 |
Committee of the Whole - Parks and Environmental Sustainability |
Receive Information |
|
10/6/2026 |
Business Meeting |
Approve |
|
10/27/2026 |
Committee of the Whole - Parks and Environmental Sustainability |
Receive Information |
Proposed Upcoming Contact(s)
|
Date |
Meeting |
Requested Action |
|
1/26/2027 |
Committee of the Whole - Parks and Environmental Sustainability |
Receive Information |
Time Constraints:
Staff continue to prioritize the rebuilding of the teen center. Legally required processes such as purchasing guidelines and bid requirements, as well as community engagement, will drive the timeline.
ANTICIPATED RESULT IF NOT APPROVED:
N/A
ATTACHMENTS:
Attachment A: Additional Project Information
Attachment B: PDB Primer for Teen Center Project
Attachment C: Teen Center Project Timelines for Council