Legislation Details

File #: CM 24-371   
Type: Committee Memo Status: Approved for Staff Report
File created: 8/6/2024 In control: Internal Committee - 3P
On agenda: 8/12/2024 Final action: 8/12/2024
Title: Approval of Ordinances Adopting Water System Plan, General Wastewater Plan Update, and Changes to RZC 21.17.010: Adequate Public Facilities and Services Required
Attachments: 1. AttA_Water System Plan and Wastewater Plan Report and Recommendation(signed), 2. AttB_2024_09-03WSP and GWP-Council Presentation

TO: Internal Committee - 3P

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Lisa Rigg

Senior Engineer

Public Works

Anne Dettelbach

Senior Planner

Public Works

Jeff Thompson

Senior Engineer

Public Works

Peter Holte

Senior Planner

 

 

TITLE:

title

Approval of Ordinances Adopting Water System Plan, General Wastewater Plan Update, and Changes to RZC 21.17.010: Adequate Public Facilities and Services Required

 

OVERVIEW STATEMENT:

recommendation

Staff recommend that the Council adopt ordinances adopting these two functional plans and amending RZC 21.17.010 as recommended by the Planning Commission on July 24, 2024 (See Attachment A and associated exhibits).

 

The City prepared the Redmond Water System Plan (WSP) to outline actions for the City to take to protect its underground drinking water resources and provide sufficient water storage and distribution to meet the drinking water, irrigation, and fire flow needs of Redmond’s residents and businesses for the next two decades.  The City also completed a “major amendment” to the 2021 General Wastewater Plan (GWP), along with related changes to RZC 21.17.010.  The wastewater functional plan has been updated using population growth projections that align with Redmond 2050.  It identifies actions the City’s Wastewater Utility will need to take to ensure that sewer system capacity matches the increased demand created by growth.  

body

☐  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

☐  Receive Information                                          ☒  Provide Direction                                          ☐  Approve

 

 

REQUEST RATIONALE:

 

•                     Relevant Plans/Policies:

Redmond 2050

Environmental Sustainability Action Plan

RCW 36.70A.070.3

King County Countywide Planning Policies PF1-4, PF-5, and PF-12

 

•                     Required:

Council approval is required for all ordinances.

WSP: Chapter 246-290-100 Washington Administrative Code (WAC)

GWP: Washington State Growth Management Act

•                     Council Request:

N/A

•                     Other Key Facts:

During the development of the GWP, the City learned of sewer capacity issues that could arise in Downtown Redmond during a 100-year peak sewer flow event due to the configuration of the King County Sewer Trunkline. As part of this GWP update, the City proposes conducting additional analysis to determine the feasibility of solutions to address this issue. To support this additional analysis, protect public health, and ensure compliance with state growth management requirements, the City drafted revised language to Redmond Zoning Code (RZC) 21.17.010: Adequate Public Facilities and Services Required. This new language establishes a threshold by identifying the total amount of remaining growth currently allowed in Downtown Redmond under the Redmond 2030 Comprehensive Plan. Once this threshold has been achieved, new downtown development projects will be required to demonstrate that their project will not exceed the sewer’s systems capacity. The revised language will sunset when the City’s studies have identified a remedy to the Downtown sewer capacity issues.

 

 

OUTCOMES:

Development and adoption of these Plans, including through the implementation of associated capital projects, ensures the City is taking appropriate actions to: protect its underground drinking water aquifer;  provide sufficient water storage and distribution to meet the community’s drinking water, irrigation, and fire flow needs; and provide wastewater collection services for its growing population.

 

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

•                     Timeline (previous or planned):

Summer 2023: LetsConnect page (WSP)

Summer 2023: Draft WSP review by neighbors, Washington Department of Ecology, Washington State Department of Health

September 13, 2023: Planning Commission Study Session (WSP)

June 12, 2024: Planning Commission Study Session (WSP and GWP)

June 26, 2024: Planning Commission public hearing and Study Session (WSP and GWP)

July 10, 2024: Planning Commission Study Session (WSP and GWP)

 

•                     Outreach Methods and Results:

LetsConnect page: one comment received

Utilities and Capital Facilities webpage: no comments received

E-news article: NA

Public Hearing: one written comment received

 

•                     Feedback Summary:

Commenters are supportive of actions taken to protect the Critical Aquifer Recharge Area

 

 

 

BUDGET IMPACT:

 

Total Cost:

Water System Plan (including Risk and Resiliency Assessment): $600,000

General Wastewater Plan: $147,533

 

 

Approved in current biennial budget:                                          ☒  Yes                                          ☐  No                                          ☐  N/A

 

Budget Offer Number:

WSP: 0000003

GWP:0000147

 

 

Budget Priority:

Healthy and Sustainable

 

Other budget impacts or additional costs:                     ☐  Yes                                          ☐  No                                          ☒  N/A

If yes, explain:

Examples: software with a yearly cost, revenue generating, match requirements, etc. - if none, enter N/A.

 

Funding source(s):

City Water and Wastewater Utility funds

 

 

Budget/Funding Constraints:

N/A

 

☐  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

Click and select a date, or click and press delete if none.

Click and select a meeting from the dropdown menu.

Click and select an action from the dropdown menu.

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

9/3/2024

Business Meeting

Provide Direction

 

Time Constraints:

The 2011 Water System Plan was due for an update by July 2024.  Department of Health has approved the delay in completion and adoption of the plan, but additional delays would be detrimental as there are Capital projects recommended in the plan that should be added to the CIP and budgeted.

 

 

 

ANTICIPATED RESULT IF NOT APPROVED:

The City will struggle to provide sufficient water and wastewater infrastructure required to accommodate planned population growth and other stressors.  

 

 

 