File #: AM No. 24-150   
Type: Consent Item Status: Passed
File created: 9/24/2024 In control: City Council
On agenda: 10/15/2024 Final action: 10/15/2024
Title: Award Construction Contract to Lakeside Industries Inc. and Approve Consultant Services Agreement Supplement 1 with David Evans and Associates, Inc. for the West Lake Sammamish Parkway Pavement Preservation (Marymoor to Leary) Project
Attachments: 1. Agenda Memo, 2. Attachment A: Project Information Sheet, 3. Attachment B: Additional Project Information, 4. Attachment C: Consultant Agreement

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Mike Haley

Project Manager

Planning and Community Development

Micah Ross

Senior Engineer

Public Works

Steven Gibbs

Capital Projects Division Manager

Public Works

Vangie Garcia

Deputy Public Works Director

 

 

TITLE:

title

Award Construction Contract to Lakeside Industries Inc. and Approve Consultant Services Agreement Supplement 1 with David Evans and Associates, Inc. for the West Lake Sammamish Parkway Pavement Preservation (Marymoor to Leary) Project

 

OVERVIEW STATEMENT:

recommendation

This project will rehabilitate the asphalt roadway on West Lake Sammamish Parkway from approximately one hundred feet north of Marymoor Way to the Leary Way NE intersection. The project scope also includes new channelization and new vehicle loop detectors.

 

Public Works requests to award the construction contract to Lakeside Industries Inc. in the amount of $1,217,250 for construction of the West Lake Sammamish Parkway Pavement Preservation (Marymoor to Leary) (Project No. 2311). Public Works also requests approving a supplemental agreement to the consultant services contract with David Evans and Associates, Inc., in the amount of $250,000 for construction engineering support services for the project. The supplemental agreement would increase the maximum amount payable for consultant services to $506,685.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Transportation Master Plan

Community Strategic Plan - Objective #1: Invest in infrastructure preservation and replacement across the city to maintain the current level of service, the reliability of capital assets, and provide timely and cost-effective replacement.

                     Required:

Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

West Lake Sammamish Parkway is a key corridor for Redmond. Approving this construction contract and supplement will allow for the contractor to rehabilitate the asphalt roadway between Marymoor Way and Leary Way NE. This project will increase the useful life of the pavement and reduce the need for ad-hoc maintenance.

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$1,217,250 Construction Contract

$250,000 Supplemental Agreement Number 1

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

FHWA Grant and Transportation CIP

 

Budget/Funding Constraints:

Use of Federal Highway grants requires a 13.5% funding participation by Redmond.

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

10/1/2024

Committee of the Whole - Planning and Public Works

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

Award of bid must occur within 45 days of the bid opening (which occurred on September 5, 2024) or the contractor may withdraw their bid.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Not approving contract will result in delaying construction, increasing the cost to complete the project.

 

 

ATTACHMENTS:

Attachment A: Pavement Preservation- West Lake Sammamish Parkway (North of Marymoor to Leary Way) Project Information Sheet

Attachment B: Additional Project Information

Attachment C: Consultant Agreement