File #: AM No. 22-039   
Type: Staff Report Status: Presented
File created: 2/15/2022 In control: City Council
On agenda: 3/15/2022 Final action: 3/15/2022
Title: Update on the Plan for and Status of the NE 40th Street Corridor Improvements from 156th Avenue NE to West Lake Sammamish Parkway
Attachments: 1. Agenda Memo, 2. Attachment A: Presentation

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Planning and Community Development

Carol V. Helland

425-556-2107

 

DEPARTMENT STAFF:

Planning and Community Development

Peter Dane

Acting Transportation Planning and Engineering Manager

Public Works

Jon Spangler

Construction Division Manager

 

 

TITLE:

title

Update on the Plan for and Status of the NE 40th Street Corridor Improvements from 156th Avenue NE to West Lake Sammamish Parkway

 

OVERVIEW STATEMENT:

recommendation

The Governance Committee approved a budget increase for the NE 40th Street Shared Use Path project that is currently in design from $4,496,340 to $5,328,676 and requested that the following information be shared with Council:

 

1)                     A status update regarding planned transportation projects on the 40th Street corridor.

2)                     The anticipated budget increase necessary to fully fund the 40th Street Shared Use Path Project between 156th Avenue NE and 163rd Avenue NE so it can advance toward an award of contract with a full project contingency.

3)                     An updated cost will be provided to Council for funding approval in late Spring/early Summer 2022 at award of the construction contract (after City has received construction bids for project).

 

Information regarding planned and proposed transportation improvements on the 40th Street corridor may be found in Attachment A.

 

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Transportation Master Plan

                     Required:

None, this request is lower than the threshold established in the CIP Proviso requiring Council approval.

                     Council Request:

N/A

                     Other Key Facts:

None

 

 

OUTCOMES:

This informational update is intended to help ensure a timely approval of the construction contract - helping avoid potential schedule delays.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

The project will be bid this spring then brought to Council for construction contract award in late spring or early summer. 

                     Outreach Methods and Results:

This NE 40th Street Corridor Improvement Project is identified in the Transportation Master Plan and approved in 2021-2026 Capital Investment Program. Direct project outreach has involved the Pedestrian Bicycle Advisory Committee and the adjacent property owner.

                     Feedback Summary:

Support for:

-                     Upgrading existing sidewalk to meet Americans with Disabilities Act standards, and

-                     Providing a new comfortable bicycle facility connecting to light rail.

 

 

BUDGET IMPACT:

 

Total Cost:

The cost estimate as of 60% design is $5,328,676, exceeding the approved 2021-2026 Capital Investment Plan budget of $4,496,340.

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP - Overlake Urban Center Investments (Map # 138)

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Transportation Impact Fees will fund anticipated increase of $832,336

 

Budget/Funding Constraints:

Transportation impact fees may only be used for new transportation facilities that are consistent with the Transportation Facilities Plan which include bike capacity expansion projects. There are transportation impact fees available to fully fund the increase in project costs.

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

6/2/2020

Business Meeting

Approve

3/1/2022

Committee of the Whole - Planning and Public Works

Receive Information

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

TBD

Business Meeting

Approve

 

Time Constraints:

This project will return to Council for award of the construction contract in late Spring or early Summer 2022.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

If the construction contract is not ultimately approved then pedestrian and bicycle improvements on 40th Street, including future projects to the east of 163rd Avenue, will be cancelled.

 

 