Skip to main content
City of Redmond Logo
File #: CM 26-066   
Type: Committee Memo Status: Referred
File created: 1/28/2026 In control: City Council
On agenda: 3/3/2026 Final action:
Title: Approve Consultant Agreement with BHC for the Viewpoint AC Watermain Replacement Project
Attachments: 1. Agenda Memo, 2. Attachment A: CIP Project Information Sheet, 3. Attachment B: Additional Project Information, 4. Attachment C: BHC Consultant Agreement

TO: Committee of the Whole - Planning and Public Works

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Shailee Jain

Senior Project Manager

Public Works

Jeff Thompson

Senior Engineer

Public Works

Chris Stenger

Deputy Public Works Director

Public Works

Steve Gibbs

Engineering Manager

 

 

TITLE:

title

Approve Consultant Agreement with BHC for the Viewpoint AC Watermain Replacement Project

 

OVERVIEW STATEMENT:

recommendation

Public Works is requesting approval of the consultant agreement with BHC in the amount of $1,200,000. This agreement is for design services for the Viewpoint AC Watermain Project, which will replace aging asbestos concrete water pipes, structurally deficient stormwater pipes, and upgrade ADA ramps within the project area.

 

Staff is seeking authorization to negotiate and acquire property rights for the project as needed.

 

Public Works is also requesting Council increase the total funding for this project from $10,555,742 to $12,619,684. This increase of $2,063,942 is for the replacement of deficient stormwater pipe in the same area as the water pipes that will be replaced. Combining the water pipe and stormwater pipe replacements into one project limits impact to residents and the travelling public and saves taxpayers due to efficiencies of combining the water and stormwater work into one construction site.

body

  Additional Background Information/Description of Proposal Attached

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Utilities Strategic Plan

Stormwater Plan

Water Systems Plan

Capital Investment Program

                     Required:

Council approval is required to award an Architectural and Engineering Services agreement that exceeds $50,000 (2018 City Resolution 1503).

Council approval is needed for real property transactions per RCW 35.A11.010

                     Council Request:

N/A

                     Other Key Facts:

Request for proposals advertised in October and November of 2025, proposals received, and evaluation of most qualified completed. BHC Consultants LLC is selected as the most qualified design consultant.

 

 

OUTCOMES:

The Viewpoint Watermain Pipe Replacement Project will replace approximately 6,000 feet of existing asbestos cement waterline that is more than 50 years old, undersized for current fire flow requirements, and prone to failure. The existing waterline has experienced numerous breaks that have resulted in flooding and damage to private property. The new waterline will be sized to meet current fire flow standards and is intended to eliminate waterline breaks within the area served. The project also includes replacement of approximately 1,400 feet of stormwater pipe with poor structural condition ratings within the project limits. ADA curb ramps within the project area will be upgraded to meet current accessibility standards. A project map is included in the consultant scope in Attachment C.

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

Public Works will work with Communications to inform local residents and Audubon Elementary School about the project and minimize impacts and disruption. See Attachment B.

                     Outreach Methods and Results:

To be determined

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$1,200,000

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Healthy and Sustainable

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

Public Works is requesting an additional $2,063,942 to complete the project. The additional funding is available due to recent cancellations of other stormwater CIP projects.

 

Funding source(s):

Water CIP, Stormwater CIP, EPA Grant.

 

Budget/Funding Constraints:

None

 

  Additional budget details attached.

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

N/A

Item has not been presented to Council

N/A

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

3/3/2026

Business Meeting

Approve

 

Time Constraints:

None

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Not approving the design contract affects the anticipated city project timeline for construction and the completion of this project would be delayed according to CIP budget documents.

 

 

ATTACHMENTS:

Attachment A: CIP Project Information Sheet

Attachment B: Additional Project Information

Attachment C: BHC Consultant Agreement