Title: CIP Project Approval - Electrical Service Upgrades and Electric Vehicle Charging Infrastructure
Attachments: 1. Agenda Memo, 2. Attachment A: CIP Business Case and Cost Estimate

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Parks

Carrie Hite

425-556-2326

 

DEPARTMENT STAFF:

Parks

Lee Ann Skipton

Facilities Manager

 

 

TITLE:

title

CIP Project Approval - Electrical Service Upgrades and Electric Vehicle Charging Infrastructure

 

OVERVIEW STATEMENT:

recommendation

Staff are seeking approval to fund a project that includes a one-time upgrade to the electrical services at two City facilities to support increased energy load, as well as the installation of electric vehicle (EV) charging stations to support the City’s growing EV fleet.

A similar project was originally proposed for the 2021-2022 CIS but was unfunded when revenue projections were reduced due to Covid-19 impacts. Since then, the scope of the project was refined to only address the power capacity and fleet charging needs.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

o                     Climate Emergency Declaration

o                     Environmental Sustainability Action Plan

o                     Green Fleet (pending)

o                     Zero Carbon Strategy (pending)

                     Required:

N/A

                     Council Request:

At the request of City Council, staff is verifying eligibility of REET funds.

                     Other Key Facts:

N/A

 

 

OUTCOMES:

This project will upgrade the electrical services at two municipal buildings to support the projected energy load through 2050. The project also includes the addition of 11 new EV charging stations; each charging station can accommodate two vehicles at a time. The proposed infrastructure will support 4 existing EVs and a minimum of 17 planned EV purchases by 2023.

 

Additional stations will be added in future CIP requests to accommodate the City’s growing EV fleet. This strategy will keep charging station installation one year ahead of the City’s green fleet goals, while remaining flexible to changes in operations, goals, or market trends. EV charging infrastructure is a foundational action as the City continues to electrify its vehicle fleet.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

2021 Planning, design, and engineering. 2022 Construction and project complete.

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$596,400

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Healthy and Sustainable

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

This work is essential to support the goals of the Public Works Fleet program. EV purchases are being held awaiting necessary infrastructure.

 

Funding source(s):

The project is proposed to be funded from a $40,000 contribution from Microsoft and unallocated REET funds.

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

10/12/2021

Committee of the Whole - Planning and Public Works

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

Completing this project is critical to continuing electrification of the City fleet.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

New fleet vehicle purchases will not be electric.

 

 

ATTACHMENTS:

Attachment A: CIP Business Case & Cost Estimate