Title: Update on Evans Creek Relocation Reed Canarygrass Removal Plan
Attachments: 1. Agenda Memo, 2. Attachment A: Reed Canarygrass Removal Evans Creek

TO: Committee of the Whole - Parks and Environmental Sustainability

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Phil Williams

425-556-2880

 

DEPARTMENT STAFF:

Public Works

Emily Flanagan

Senior Engineer

 

 

TITLE:

title

Update on Evans Creek Relocation Reed Canarygrass Removal Plan

 

OVERVIEW STATEMENT:

recommendation

Update the Council on the City’s approach for controlling invasive plants on the Evans Creek Project.  Provide information to prepare them for potential questions that may arise from the work.  Hear questions and concerns about approach.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

-                     Natural Features Element of the Comprehensive Plan

-                     Shoreline Master Program

-                     RZC 21.64.020.F.17

-                     RZC.68.170.B.5

-                     Proposed Integrated Pest Management Plan - City of Redmond

                     Required:

N/A

                     Council Request:

N/A

                     Other Key Facts:

This update is being brought forth due to the known concerns of Council and City residents about the use of herbicides near critical areas.

 

 

OUTCOMES:

Removing the Reed Canary grass will help set up the Evans Creek Relocation project for success in meeting its permitted mitigation metrics for native plant establishment. 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

Before and during removal (removal planned to start April/June timeframe)

                     Outreach Methods and Results:

o                     Post Signs

o                     Information on Project Website

o                     Provide Background Information to Communications, Customer Service, and Mayor’s Office to facilitate response to residents’ comments.

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

Anticipated cost ~$20,000 for Reed Canary grass Removal. 

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

CIP

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Stormwater CIP - Evans Creek Relocation Project Budget

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

N/A

Item has not been presented to Council

N/A

 

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

Planning on starting removal work in April/June 2022.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Not requesting approval, just providing an update.

 

 

ATTACHMENTS:

Attachment A - Reed Canarygrass Removal Evans Creek