File #: AM No. 22-054   
Type: Consent Item Status: Passed
File created: 3/22/2022 In control: City Council
On agenda: 4/19/2022 Final action: 4/19/2022
Title: Award of Bid to CDK Construction Services, Inc. in the Amount of $1,944,729, Approval of Agreement Supplement No. 3 with Reid Middleton in the Amount of $149,854, and Approval of FEMA Grant for Fire Station 16 Seismic Upgrade
Attachments: 1. Agenda Memo, 2. Attachment A: Vicinity Map, 3. Attachment B: Additional Project Information, 4. Attachment C: Consultant Services Agreement Supplement 3 with Reid Middleton, 5. Attachment D: FEMA Grant Agreement

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Phil Williams

425-556-2880

 

DEPARTMENT STAFF:

Public Works

Jon Spangler

Construction Division Manager

Public Works

Joseph O’Leary

Project Manager

 

 

TITLE:

title

Award of Bid to CDK Construction Services, Inc. in the Amount of $1,944,729, Approval of Agreement Supplement No. 3 with Reid Middleton in the Amount of $149,854, and Approval of FEMA Grant for Fire Station 16 Seismic Upgrade

B

 

OVERVIEW STATEMENT:

Award a construction contract to CDK Construction Services, Inc. of Duvall, WA, in the amount of $1,944,729 for construction of Fire Station 16 and Maintenance Facility Building Seismic Upgrade project (Project Number 60021819).

 

Approve Consultant Services Agreement Supplement No. 3 with Reid Middleton in the amount of $149,854 for construction engineering support services and increase the maximum amount payable under this contract to $810,502.

 

Accept a FEMA grant award for the Fire Station 16 and Maintenance Facility construction phase up to a maximum amount of $2,442,862. We are currently waiting to receive the final grant contract for signature by the City. We expect it to arrive within the next 10 days. We have already been notified of the grant award and would ask council to authorize the mayor to sign it if the agreement is what we are expecting in terms of the dollar amount and attached conditions.

 

Increase the City’s contribution to the project budget by $21,499 (General Fund).

 

recommendation

 

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

N/A

                     Required:

Council approval is required to award Public Works Contracts and Architectural and Engineering Services agreements that exceed $50,000 (2018 City Resolution 1503) and Council approval is needed for grant acceptance per RCW 35A.11.040.

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

Completion of this project will enable fire operations to better respond to Redmond citizens and businesses in an emergency after the occurrence of an earthquake.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$3,096,436

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

General Funding, FEMA Grant

 

Budget/Funding Constraints:

FEMA funding constraints not to exceed $2,442,862.

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

4/5/2022

Committee of the Whole - Planning and Public Works

Approve

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

 

None proposed at this time

 

 

Time Constraints:

Award of bid must occur within 45 days of bid opening or the contractor may withdraw their bid. Bids were opened on March 10; award must occur by April 24.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Project construction would not move forward, and fire station and maintenance building would not be protected from a seismic event.

 

FEMA Grant funds would be forfeited.

 

 

ATTACHMENTS:

Attachment A: Fire Station 16 Vicinity Map

Attachment B: Additional Project Information

Attachment C: Consultant Services Agreement Supplement 3 with Reid Middleton

Attachment D: FEMA Grant Agreement