TO: Committee of the Whole - Public Safety and Human Services
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
|
Parks |
Loreen Hamilton |
425-556-2336 |
|
Public Works |
Chris Stenger |
425-403-5510 |
DEPARTMENT STAFF:
|
Public Works |
Shailee Jain |
Project Manager |
|
Public Works |
Eric Dawson |
Engineering Supervisor |
|
Public Works |
Steve Gibbs |
Capital Division Manager |
|
Parks |
Danika Globokar |
Deputy Parks Director |
TITLE:
title
Award Progressive Design-Build (PDB) Contract to Lease Crutcher Lewis WA, LLC of Seattle, Washington, for the Teen Center Project
recommendation
OVERVIEW STATEMENT:
Parks and Public Works are requesting to award the PDB Contract for the Teen Center Project, Project No. 2571, to Lease Crutcher Lewis WA, LLC in the amount of $1,486,030 for the completion of the Validation Phase Work.
The PDB Contract requires the Design-Builder to perform all design and construction services. The Work will be completed in three phases: the Phase 1a Validation Phase, Phase 1b (Preconstruction and Design), and Phase 2 (Construction).
Approval is currently being requested for the entire PDB Contract, with funding limited to the Validation Phase scope of Work. Future funding requests for Phases 1b and 2 will be submitted to the Council as Contract Amendments before any further work is started.
The City conducted a competitive Progressive Design-Build selection process in accordance with RCW 39.10, resulting in the selection of Lease Crutcher Lewis WA, LLC as the highest-scoring team. The team demonstrated relevant project experience, a strong approach to teen-centered community engagement, and an understanding of the Teen Center’s project goals and priorities.
For reference: PDB lets the City hire one accountable team of architects and builders early (Design-Builder team), chosen for their qualifications, and then shape the project's scope, schedule and price together with that team before committing to a final construction price. A primer regarding the PDB process for the Teen Center is provided under a separate agenda item on 11/17.
body
☒ Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
☐ Receive Information ☐ Provide Direction ☒ Approve
REQUEST RATIONALE:
• Relevant Plans/Policies:
Parks, Arts, Recreation, Culture, and Conservation Plan (PARCC); Teen Services Engagement Report (2025); Community Priorities for the Future of Redmond’s Community Centers (2017)
• Required:
Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503). Council Action AM No 25-184:
“Approval to Rebuild the Teen Center on the Same Location. Prioritize Expedience in Construction, Centering Teen Voices in the Design Process, and Including Music Performance Space and a Dedicated Recording Studio to Continue the Old Firehouse Teen Center Legacy”
• Council Request:
N/A
• Other Key Facts:
Parks and Public Works are requesting this item go forward for Council approval at the December 1, 2026, Council business meeting.
OUTCOMES:
Approving this action keeps the City on the path to implementation of the Teen Center project.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
• Timeline (previous or planned):
Community engagement will be a key part of the project moving forward. Engagement will be discussed in monthly project updates to Council.
• Outreach Methods and Results:
N/A
• Feedback Summary:
N/A
BUDGET IMPACT:
Total Cost:
$1,486,030
Approved in current biennial budget: ☐ Yes ☒ No ☐ N/A
The budget shown in the PIS aligns with what is in the proposed 2027-2032 CIP
Budget Offer Number:
545
Budget Priority:
Healthy and Sustainable
Other budget impacts or additional costs: ☐ Yes ☒ No ☐ N/A
If yes, explain:
N/A
Funding source(s):
Bond Proceeds, General Fund, Grant (potential regional partners), Impact Fees, General Govt/Facilities CIP, Real Estate Excise Tax, pending approval of the 2027-2032 CIP
Budget/Funding Constraints:
N/A
☐ Additional budget details attached
COUNCIL REVIEW:
Monthly updates are being provided to Council on this project. This contract is being brought to the Council for the first time.
Previous Contact(s)
|
Date |
Meeting |
Requested Action |
|
N/A |
Item has not been presented to Council |
N/A |
Proposed Upcoming Contact(s)
|
Date |
Meeting |
Requested Action |
|
12/1/2026 |
Business Meeting |
Approve |
Time Constraints:
N/A
ANTICIPATED RESULT IF NOT APPROVED:
Without approval of the PDB Contract, the project cannot advance into Validation, design, and construction, putting the compressed schedule at greater risk and increasing the potential for delays and cost escalation.
ATTACHMENTS:
Attachment A: Teen Center Project Information Sheet
Attachment B: Additional Project Information
Attachment C: Progressive Design-Build Contract