File #: AM No. 25-130   
Type: Consent Item Status: Agenda Ready
File created: 8/26/2025 In control: City Council
On agenda: 9/16/2025 Final action:
Title: Award of Construction Contract to Fury Site Works Inc., of North Bend, WA, in the Amount of $820,885, for the Sidewalk Repairs Avondale Way Project
Attachments: 1. Attachment A: Project Information Sheet, 2. Attachment B: Additional Project Information

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Joe Averill

Project Manager

Planning and Community Development

Micah Ross

Senior Engineer

Public Works

Steve Gibbs

Capital Division Manager

Public Works

Vangie Garcia

Deputy Public Work Director

 

 

TITLE:

title

Award of Construction Contract to Fury Site Works Inc., of North Bend, WA, in the Amount of $820,885, for the Sidewalk Repairs Avondale Way Project

 

OVERVIEW STATEMENT:

 

recommendation

Award Construction Contract

Public Works is requesting to award the construction contract of the Sidewalk Repairs Avondale Way (Project Number 2429) to Fury Site Works Inc. in the amount of is $820,885.

 

This project will repair sidewalks to enhance pedestrian safety and accessibility. Work will focus on the south side of Avondale Way, from 170th Ave NE to where the sidewalk intersects the Bear Creek Trail (approximately 1000 feet), and on the north side of Avondale Way, extending approximately 600 feet east from NE 79th St. to the concrete retaining wall.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

  • Relevant Plans/Policies:

Transportation Master Plan, ADA Transition Plan, PARCC Plan, Tree Canopy Plan, Climate Resiliency and Sustainability Vegetation Management Plan

  • Required:

 Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City

Resolution 1503).

  • Council Request:

NA

  • Other Key Facts:

Public Works is requesting this item go forward for Council approval at the September 16, 2025, Council business meeting.

 

 

OUTCOMES:

Approving the contract will provide for new ADA compliant sidewalks that will meet the public right-of-way accessibility guidelines and will also meet the city’s mission to create vibrant, connected, healthy, and sustainable urban areas.

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

  • Timeline (previous or planned):

Webpage: Initial posting spring 2025

Postcard: First mailing spring 2025

Social Media: Posts and service alerts updates will be provided.

On-site signage: Project information and tree protection signs, during construction.

  • Outreach Methods and Results:

NA

  • Feedback Summary:

NA

 

 

BUDGET IMPACT:

 

Total Cost:

$820,885

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

General Fund, Transportation CIP

 

Budget/Funding Constraints:

NA

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

9/2/2025

Committee of the Whole - Planning and Public Works

Receive Information

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

Award of bid must occur within 45 days of the bid opening, or the contractor may withdraw their bid.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Not approving the contract will result in delaying the construction and increasing the cost to complete the project.

 

 

ATTACHMENTS:

Attachment A: Sidewalk Repairs Avondale Way Project Information Sheet

Attachment B: Additional Project Information