File #: AM No. 25-021   
Type: Consent Item Status: Passed
File created: 1/27/2025 In control: City Council
On agenda: 3/4/2025 Final action: 3/4/2025
Title: Approval of Consultant Agreement with HDR, in the Amount of $1,200,000, for the Avondale Road Pavement Management and Waterline Upgrade (NE 90th St to Novelty Hill Road) Project
Attachments: 1. Agenda Memo, 2. Attachment A: HDR Consultant Agreement, 3. Attachment B: Public Information Sheet

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Jeff Thompson

Senior Engineer

Public Works

Deepali Jodh

Senior Project Manager

Public Works

Adnan Shabir

Senior Engineer

Public Works

Doug De Vries

Utility Engineering Manager

Public Works

Patty Criddle

Engineering Supervisor

Public Works

Steve Gibbs

Capital Projects Manager

 

 

TITLE:

title

Approval of Consultant Agreement with HDR, in the Amount of $1,200,000, for the Avondale Road Pavement Management and Waterline Upgrade (NE 90th St to Novelty Hill Road) Project

OVERVIEW STATEMENT:

recommendation

This consultant agreement with HDR in the amount of $1,200,000 is for design services for the Pavement Management and Waterline Upgrade - Avondale Road (NE 90th St to Novelty Hill Road) Project, Project 2403.

 

Avondale Road is a key corridor for Redmond and the roadway pavement as well as the underground water pipes have reached the end of their useful life. In addition to the rehabilitation of the asphalt roadway, this project includes replacing 2,200 feet of water main, completion of bike lanes along this corridor, and installation of new roadway channelization and pedestrian ramps.

body

  Additional Background Information/Description of Proposal Attached

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

CIP Project and Community Strategic Plan - Objective #1: Invest in infrastructure preservation and replacement across the City to maintain the current level of service, the reliability of capital assets, and provide timely and cost-effective replacement.

                     Required:

Council approval is required to award an Architectural and Engineering Services agreement that exceeds $50,000 (2018 City Resolution 1503).

                     Council Request:

N/A

                     Other Key Facts:

A competitive procurement process was conducted in July and August of 2024 to select the consultant. A Request for Proposals (RFP) was advertised, proposals were received, and evaluation of most qualified was completed. HDR Engineering was selected as the most qualified design consultant.

 

 

OUTCOMES:

After construction is complete, this project will extend the lifespan of both the waterline system and the pavement, while also enhancing roadway safety for pedestrians, bicyclists, and motor vehicles. The existing channelization will be improved through the addition of bike lanes and enhanced pedestrian safety features, such as new crosswalks and narrower travel lanes.

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$1,200,000

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

General Fund, Transportation Benefit District, Transportation CIP, and Water CIP

 

Budget/Funding Constraints:

None

 

  Additional budget details attached.

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

2/4/2025

Committee of the Whole - Planning and Public Works

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

None

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Not approving the design contract affects the anticipated city project timeline for construction and the completion of this project would be delayed according to CIP budget documents. While delayed, pavement conditions would continue to deteriorate and increase the chances of a water pipe burst. 

 

 

ATTACHMENTS:

Attachment A: HDR Consultant Agreement for Avondale Road Pavement Overlay and Waterline Replacement

Attachment B: Pavement Mgmt. - Avondale (90th to NHR) PIS