File #: AM No. 25-091   
Type: Consent Item Status: Passed
File created: 5/12/2025 In control: City Council
On agenda: 6/3/2025 Final action: 6/3/2025
Title: Southeast Redmond Market Study Consultant Contract Approval
Attachments: 1. Agenda Memo, 2. Attachment A: Consulting Services Agreement - SE Redmond Market Study with Attachments

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Planning and Community Development

Carol Helland

425-556-2107

 

DEPARTMENT STAFF:

Planning and Community Development

Lauren Alpert

Senior Planner

Planning and Community Development

Jeff Churchill

Long Range Planning Manager

Planning and Community Development

Seraphie Allen

Deputy Director

 

 

TITLE:

title

Southeast Redmond Market Study Consultant Contract Approval

 

OVERVIEW STATEMENT:

recommendation

Staff recommends approving a contract with Berk for the Southeast Redmond Market Study for $74,968.

This work was approved in the budget using one-time funds and supports an application for a countywide manufacturing and industrial center in Southeast Redmond. 

 

The BERK team will take a holistic approach that integrates land use considerations, access, transportation, sustainability, infrastructure needs, economic development goals, and market demand drivers to develop an informed market study for the center.

 

The scope of work has been updated to include a review of Redmond’s sustainability goals. Sustainability was added to the introduction and approach of the scope of work on page 1 and added into Task 2 for stakeholder engagement on page 2.  Task 6 on page 4 of the scope of work has been updated to include trade-offs in the final strategy guide.

 

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Redmond 2050 establishes the intent to create a countywide Southeast Redmond Manufacturing and Industrial Center (SE-MIC). As part of the application process with King County, Redmond is conducting a market study to strengthen the City’s application.

                     Required:

N/A

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

The outcome is a strong countywide center application and recommendations to the City for a strong SE Redmond economic center.

 

Deliverables of the study include:

                     Engagement plan and support with materials as the plan is developed

                     Existing conditions report that includes a description of key market drivers

                     List of six industries for analysis

                     Business opportunities analysis findings

                     Data used in analysis in native form

                     List of potential and shovel-ready sites for analysis (up to five) and analysis findings

                     Strategy Guide

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

The study is scheduled to have a kick-off in June and be completed by December 2025. Major deliverables will be completed in August, September, and October.

                     Outreach Methods and Results:

Berk and the City will develop and deliver a stakeholder engagement plan that aligns with the project needs and available resources. This will include outlining engagement objectives, project information needs, all virtual and in-person engagement activities, facilitation responsibilities, materials requirements, and the engagement timeline. External stakeholders will include existing businesses and property owners, businesses in Redmond and businesses seeking industrial property in the area, industrial property real estate professionals, and partners in economic development.

                     Feedback Summary:

N/A - project has not started. 

 

 

BUDGET IMPACT:

 

Total Cost:

$74,968

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

0000304 - Community/Economic Development

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

General Fund

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

5/20/2025

Committee of the Whole - Public Safety and Human Services

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

 

None proposed at this time

N/A

 

Time Constraints:

The center application to King County is due October 1. The market study supports the application.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Delay in creation of the SE Redmond MIC.

 

 

ATTACHMENTS:

Attachment A: Consulting Services Agreement - SE Redmond Market Study with attachments