File #: CM 22-346   
Type: Committee Memo Status: Presented
File created: 4/27/2022 In control: Committee of the Whole - Planning and Public Works
On agenda: 5/3/2022 Final action: 5/3/2022
Title: Redmond Senior and Community Center Construction Contract Format
Attachments: 1. Agenda Memo, 2. Attachment A: Community and Stakeholder Involvement and Outreach, 3. Attachment B: Council Review Previous Contacts, 4. Attachment C: MACC timeline

TO: Committee of the Whole - Planning and Public Works

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Phil Williams

425-556-2880

Parks

Loreen Hamilton

425-556-2336

 

DEPARTMENT STAFF:

Public Works

Jon Spangler

Construction Division Manager

Public Works

Eric Dawson

Senior Engineer

 

 

TITLE:

title

Redmond Senior and Community Center Construction Contract Format

 

OVERVIEW STATEMENT:

recommendation

Staff is requesting input on, and approval of, the proposed Redmond Senior and Community Center construction contract format. To meet schedule deadlines, the construction contract will be divided into 3 separate Maximum Allowable Construction Costs (MACC) elements. Staff is proposing that the construction contract for MACC 1 include estimated amounts for MACCs 2 and 3 that can subsequently be executed by Mayor signature as long as the bids for MACCs 2 and 3 are below the estimated amounts approved with MACC 1.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

o                     Envision Redmond Senior Center Building Stakeholders Report March 2020

o                     Redmond Community Strategic Plan

o                     2017 Community Priorities for the Future of Redmond’s Community Centers Report

o                     Redmond Comprehensive Plan

o                     Redmond Parks, Arts, Recreation, Culture, and Conservation (PARCC) Plan

o                     Redmond Facilities Strategic Management Plan

o                     2017-2022 Redmond Capital Investment Program (CIP). Redmond Zoning Code 21.10.070B

                     Required:

City Comprehensive Plan: FW-23, CC-12, PR-19, PR-35, PR-36, PR-37, PR-38, UC-19, UC-20, DT-12, and DT-15, Redmond Zoning Code-RZC 21.10.070, RCW 39.10

                     Council Request:

N/A

                     Other Key Facts:

The GC/CM construction contract we are using for this project is based on the University of Washington’s GC/GM contract that has been used successfully on a number of projects and has been reviewed and edited by the City’s construction attorney.

 

We expect the construction contract to go forward at the May 24, 2022, Parks and Environmental Services Committee of the Whole meeting and subsequently for approval at the June 7, 2022, business meeting so that we can issue a notice to proceed with construction by mid-June.

 

 

OUTCOMES:

Receive direction and approval for the award of the construction contract approach.  Approval of the format will minimize schedule risk.

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

See Attachment A - Community and Stakeholder Involvement and Outreach

                     Outreach Methods and Results:

See Attachment A - Community and Stakeholder Involvement and Outreach

                     Feedback Summary:

See Attachment A - Community and Stakeholder Involvement and Outreach

 

 

BUDGET IMPACT:

 

Total Cost:

$48 million

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Infrastructure, Healthy and Sustainable, Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

2023-2024 CIP:  $17.116 million

State Capital Adopted Budget:  $1.25million

Surplus Park Impact Fees from 2019-2020:  $1.648 million

Surplus REET from 2019-2020:  $2.486 million

General Fund available cash from the 2019-2020 biennium and the 2021 fiscal year, surplus REET and park impact fees from the 2021 fiscal year: $9.5 million

Councilmanic bonds:  $16 million

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

N/A

See Attachment B: Council Review Previous Contacts

N/A

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

5/24/2022

Committee of the Whole - Parks and Environmental Sustainability

Approve

6/7/2022

Business Meeting

Approve

 

Time Constraints:

City staff is striving to minimize schedule risk to meet the promised facility opening date in late 2023.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Waiting for hard bids on all three MACCs before council approval of the construction contract would delay the project completion by approximately 4-6 months and push the opening into 2024.

 

 

ATTACHMENTS:

Attachment A - Community and Stakeholder Involvement and Outreach

Attachment B - Council Review Previous Contacts

Attachment C - MACC Timeline