Legislation Details

File #: AM No. 26-A147 PW   
Type: Consent Item Status: Agenda Ready
File created: 4/14/2026 In control: City Council
On agenda: 5/19/2026 Final action:
Title: Approval of the Final Contract with Road Construction Northwest and Acceptance of Construction for the 152nd Street Improvements Project, in the Amount of $6,608,175.98
Attachments: 1. Agenda Memo, 2. Attachment A: 152nd Ave NE Project Information Sheet, 3. Attachment B: Additional Project Information

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Brandon Buehler

Deputy Director

Public Works

Steve Gibbs

Division Manager

Planning and Community Development

Micah Ross

Senior Planner

Public Works

Aaron Noble

Project Manager

 

 

TITLE:

title

Approval of the Final Contract with Road Construction Northwest and Acceptance of Construction for the 152nd Street Improvements Project, in the Amount of $6,608,175.98

 

OVERVIEW STATEMENT:

recommendation

Public Works is requesting Council to approve the final contract and accept construction for the 152nd Street Improvements project (No. 1530). This contract with Road Construction Northwest had a base bid amount of $6,718,339.05, plus or minus change orders and bid items increases or decreases, resulting in a final contract amount of $6,608,175.98.

 

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Transportation Master Plan

                     Required:

Council approval is required to accept a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)

                     Council Request:

N/A

                     Other Key Facts:

Public Works is requesting this item go forward for Council approval at the May 19, 2026, Council business meeting.

 

 

 

OUTCOMES:

This project upgraded 152nd Ave NE to meet the Overlake Village Design Guidelines. These improvements increased travel choices within the redeveloping neighborhood and improved access to the Overlake Village Light Rail Station. This work included a building a bicycle and pedestrian path, ADA curb ramp improvements, signal changes, and stormwater upgrades.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$6,608,175.98

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Federal Grant, Impact Fees, Real Estate Excise Tax, Sound Transit Grant, General Fund

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

5/5/2026

Committee of the Whole - Planning and Public Works

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

Following project acceptance, in accordance with RCW 60.28, the contract retainage will be released upon receipt of clearances from the Washington State Departments of Revenue and Labor and Industries, and a mandatory 45-day waiting period for filing claims and liens.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

The warranty period begins upon Council acceptance. Not accepting construction will result in delay of warranty start, increasing the project close-out cost.

 

 

ATTACHMENTS:

Attachment A - Project Information Sheet

Attachment B - Additional Project Information