Title: Approval of the Final Contract with NPM Construction, in the Amount of $314,522, and Acceptance of Construction for the Three Rapid Rectangular Flashing Beacon Crosswalks Project
Attachments: 1. Agenda Memo, 2. Attachment A1: Pedestrian Crossing 116th and 159th Project Information Sheet and Vicinity Map, 3. Attachment A2: RRFB 180th-70th and Bear Creek-159th Project Information Sheet and Vicinity Map, 4. Attachment B: Additional Project Information

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Rob Crittenden

Project Manager

Public Works

Gina Schroeder

Program Administrator

Public Works

Steve Gibbs

Interim Engineering Manager

 

 

TITLE:

title

Approval of the Final Contract with NPM Construction, in the Amount of $314,522, and Acceptance of Construction for the Three Rapid Rectangular Flashing Beacon Crosswalks Project

 

OVERVIEW STATEMENT:

recommendation

The Three Rapid Rectangular Flashing Beacon (RRFB) Crosswalks Project consists of intersection improvements at NE 116th Street and 159th Ave NE, Bear Creek Parkway and 159th Place NE, and 180th Ave NE and NE 70th Street.  The contract with NPM Construction combined two projects in the CIP (Project Nos. 2116-316-03 and 2117-316-03) for a total bid amount of $335,338.

 

The final contract amount, even after taking into account plus or minus change orders and bid item increases or decreases is $314,522 (under budget). Staff requests Council to accept construction of this project in order to proceed with the appropriate project close-out proceedings.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

N/A

                     Required:

Council approval is required to accept a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

This project improves the safety of pedestrian street crossings at NE 116th St and 159th Ave NE, Bear Creek Parkway and 159th Pl NE, and 180th Ave NE and NE 70th St.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$314,522

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

CIP

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

3/21/2023

Business Meeting

Approve

2/6/2024

Committee of the Whole - Planning and Public Works

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

 

None proposed at this time

N/A

 

Time Constraints:

Following project acceptance, in accordance with RCW 60.28, the contract retainage will be released upon receipt of clearances from the Washington State Departments of Revenue and Labor and Industries, and a mandatory 45-day waiting period for filing claims and liens.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

The warranty period begins upon Council acceptance. Not accepting construction will result in delay of warranty start, increasing the project close-out cost.

 

 

ATTACHMENTS:

Attachment A1: TSIP - Ped Xing 116th and 159th PIS and Vicinity Map

Attachment A2: TSIP - RRFB 180th-70th and Bear Cr-159th PIS and Vicinity Map

Attachment B: Additional Project Information