Skip to main content
City of Redmond Logo
File #: AM No. 25-095   
Type: Consent Item Status: Passed
File created: 5/28/2025 In control: City Council
On agenda: 6/17/2025 Final action: 6/17/2025
Title: ??Approval of a Consultant Agreement with Consor, in the Amount of $435,515, for the Willows Road Watermain Extension (NE 116th St to NE 124th St) Project?
Attachments: 1. Agenda Memo, 2. Attachment A: Project Information Sheet, 3. Attachment B: Consultant Agreement

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Lisa Rigg

Senior Engineer

Public Works

John Mork

Senior Engineer

Public Works

Doug De Vries

Utility Engineering Manager

Public Works

Steve Gibbs

Capital Projects Division Manager

Public Works

Chris Stenger

Deputy Director

 

 

TITLE:

title

​​Approval of a Consultant Agreement with Consor, in the Amount of $435,515, for the Willows Road Watermain Extension (NE 116th St to NE 124th St) Project​

 

OVERVIEW STATEMENT:

recommendation

Public Works is requesting approval of a consultant agreement with Consor in the amount of $435,515 for design services for the Willows Road Watermain Extension (NE 116th St to NE 124th St) Project, Project 2210. The City has committed to construct 1300 linear feet (LF) of 12-inch watermain in an interlocal agreement with City of Kirkland as a part of the Proctor Willows Development.

 

Tri Pointe Homes Washington entered into a Voluntary Agreement for Payment of Funds in Lieu of Frontage Improvements for $828,000 ($328,000 for road widening, sidewalk and planter strip improvements and $500,000 for culvert replacement triggered by the frontage improvements) as part of the Proctor Willows Phase 3 Development.  This work was originally included in the scope of the Willows Road Watermain Improvement project.  Following the project kickoff, it was determined by staff that the frontage improvements and associated mitigation would cost substantially more than the contribution amount and would add permitting that would push the project out significantly beyond the planned project timeline.  A request was presented to the Governance Committee to allow the watermain extension to move forward without the sidewalk and mitigation work.  On April 17th the Governance Committee approved the revised project scope.  The watermain extension is required to be completed in 2026 per an Interlocal Agreement with Kirkland and a also needed to serve customers along Willows Road that currently do not have access to City of Redmond water.  To allow the watermain work to stay on schedule, the frontage improvement work and associated mitigation will be done as a separate project in the future. 

 

​Three consultant Statement of Qualification (SOQ) documents were selected from the MRSC roster for Engineering Services.  The SOQs were reviewed and rated by three stakeholders to select a consultant. Consor‘s SOQ was rated the highest for this project.  A scope and budget was then developed with Consor to move forward. ​ 

body

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Water System Plan

                     Required:

​​Council approval is required to award an Architectural and Engineering Services agreement that exceeds $50,000 (2018 City Resolution 1503)​

                     Council Request:

N/A

                     Other Key Facts:

​​Per the Interlocal Agreement with City of Kirkland dated March 31, 2021, the City of Redmond is required to construct the Willows Road Watermain Extension by December 31, 2026. 

 

The watermain design will take into account the need to replace the culverts in the future and will be constructed to minimize any possible future conflict with culvert construction.

 

 

OUTCOMES:

​​The project will provide a section of 12” watermain in Willows Road that will provide direct service to several parcels and will increase the looping of the system, resulting in improved water system reliability and fire protection.  ​

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

​​$435,515​

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

​​Healthy and Sustainable​

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Water CIP

 

Budget/Funding Constraints:

None

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

6/3/2025

Committee of the Whole - Planning and Public Works

Approve

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

​​The Interlocal Agreement with Kirkland requires completion of construction by December 31, 2026.​

 

 

ANTICIPATED RESULT IF NOT APPROVED:

​​Not approving the design contract affects the anticipated city project timeline for construction and the completion of this project would be delayed according to CIP budget documents.  The city would not be in compliance with the conditions of the Interlocal Agreement with Kirkland.​

 

 

ATTACHMENTS:

​​Attachment A: CIP Project Information Sheet

​Attachment B: Consor Consultant Agreement​