File #: AM No. 25-A367 PW   
Type: Consent Item Status: Agenda Ready
File created: 10/15/2025 In control: City Council
On agenda: 11/18/2025 Final action:
Title: ?Approval of a Consultant Agreement with David Evans and Associates, Inc. in the Amount of $701,960, and Acceptance of the Department of Commerce Grant for the Idylwood Park Parking Lot Expansion and Frontage Improvements Project
Attachments: 1. Attachment A: Project Information Sheet, 2. Attachment B: Consultant Agreement, 3. Attachment C: Notification of Grant Award

TO: Committee of the Whole - Planning and Public Works

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Vangie Garcia

Deputy Public Works Director

Public Works

Steve Gibbs

Capital Construction Division Manager

Parks

Dave Tuchek

Parks and Recreation Deputy Director

Parks

Lindsey Falkenburg

Parks Planning Manager

Planning and Community Development

Micah Ross

Senior Engineer

Public Works

John Mork

Project Manager

 

 

TITLE:

title

​Approval of a Consultant Agreement with David Evans and Associates, Inc. in the Amount of $701,960, and Acceptance of the Department of Commerce Grant for the Idylwood Park Parking Lot Expansion and Frontage Improvements Project

 

OVERVIEW STATEMENT:

recommendation

​​Public Works is requesting to approve the consultant agreement with David Evans and Associates, Inc. in the amount of $701,960. This agreement is for design for the Idylwood Park Parking Lot Expansion and Frontage Improvements project, Project No. 2371.

​Public Works is also requesting to accept Department of Commerce grant in the amount of $215,000. The Department of Commerce will retain three percent to cover administrative costs, resulting in a net award to the City of $208,550.

​This project will include expansion and renovation of the Idylwood Park main parking lot to increase capacity and address pavement failures, drainage issues, damaged curb, and ADA deficiencies. Pedestrian and cyclist safety enhancements will also be made along the park frontage. ​

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

​​Capital Investment Program, PARCC Plan, ADA Transition Plan​

                     Required:

​​Council approval is required to award an Architectural and Engineering Services agreement that exceeds $50,000 (2018 City Resolution 1503)

​The City Council must approve grant acceptance​

                     Council Request:

N/A

                     Other Key Facts:

​​Public Works is requesting this item go forward for Council approval at the November 18, 2025, Council business meeting​

 

 

OUTCOMES:

This project will repair and expand the park parking lot, improve accessibility and add safety improvements along West Lake Sammamish Parkway

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

​​City Communications, Parks and Public Works staff will alert park users, local residences and commuters to construction impacts prior to work beginning ​

                     Outreach Methods and Results:

​Social media, email, postcards, message boards, etc. as appropriate

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

​​$701,960 (consultant agreement)

​$208,550 (grant funding)​

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Real Estate Excise Tax, Parks CIP, Transportation, Grant

 

Budget/Funding Constraints:

None

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

11/3/2025

Committee of the Whole - Planning and Public Works

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

N/A

 

 

ANTICIPATED RESULT IF NOT APPROVED:

​​Not approving the design contract affects the anticipated city project timeline for construction and the completion of this project would be delayed according to CIP budget documents.​

 

 

ATTACHMENTS:

​​Attachment A: Idylwood Park Parking Lot Expansion and Frontage Improvements Project Information 

​Sheet

​Attachment B: David Evans and Associates, Inc. Consultant Agreement 

​Attachment C: Notification of Grant Award ​