Skip to main content
City of Redmond Logo
File #: AM No. 19-094   
Type: Consent Item Status: Passed
File created: 5/1/2019 In control: City Council
On agenda: 6/18/2019 Final action: 6/18/2019
Title: Acceptance of Construction for Mackey Creek Restoration Project with Olson Brothers Excavating, Inc. of Puyallup, Washington, and Approval of the Final Contract in the Amount of $498,622.09, City project No. 20021402
Attachments: 1. Agenda Memo No. 19-094, 2. Attachment A: Vicinity Map

MEMO TO:                     Members of the City Council

FROM:                     Mayor John Marchione

SUBJECT:                     


title

Acceptance of Construction for Mackey Creek Restoration Project with Olson Brothers Excavating, Inc. of Puyallup, Washington, and Approval of the Final Contract in the Amount of $498,622.09, City project No. 20021402

 

I.                     RECOMMENDED ACTION

recommendation


Approve the final contract amount with Olson Brothers Excavating, Inc. of Puyallup, Washington, for the base bid amount of $ 537,430, plus or minus change orders and bid items increase or decreases, resulting in a final contract amount of $ 498,622.09 and accept construction of Mackey Creek Restoration project, City project No. 20021402 as of
June 18, 2019.    

body

II.                     DEPARTMENT CONTACTS

 

Kristi Wilson, Interim Public Works Director                                             425-556-2733

Tom Hardy, Stream and Habitat Planner                                                     425-556-2762

Bassam Al-Ali, Project Manager                                                                  425-556-2743

 

III.                     DESCRIPTION/BACKGROUND

 

Project Purpose

 

The constructed project provided enhancement to Mackey Creek and its associated riparian and wetland habitat.

 

This project re-aligned approximately 700 lineal feet of the main stem of Mackey Creek and stabilized the Creek with large woody materials and habitat boulders thus encouraging formation of habitat features along the main stem and throughout the creek.

 

Project Description

 

Construction of Mackey Creek project began in August 20, 2018 and was substantially completed on October 22, 2018. Mackey Creek project was under Contract suspension on November 2, 2018 to allow for seed, fertilizer, and mulch work to be done during the allowed working dates for application. Mackey Creek project reached physical completion in April 29, 2019. The construction time frame was within the allotted days specified in the contract.      

 

IV.                     PREVIOUS DISCUSSIONS HELD

 

Planning and Public Works Committee     Design                    1/13/2015

City Council                                               Design                     6/16/2015

Planning and Public Works Committee     Update                    5/08/2018

City Council                                               Award                      7/3/2018

Accept Construction                                                                   Today

 

V.                     IMPACT

 

A.                     Service/Delivery:

 

This project enhanced Mackey Creek and wetlands in Farrel- McWhirter Park by removing fish passage barriers, reducing channel erosion and sediment deposition problems, restoring more diverse stream habitat, reducing flooding, enhancing native plant communities and removing invasive plant species.      

 

B.                     Fiscal Note:

 

Estimated costs for the project are shown below.

 

Current project Budget:

 

Storm CIP                                           $1,159,942

King County District funds                $130,000

Total funding =                                   $1,289,942

 

Estimated project Cost:

 

Design phase                                      $505,318

Construction Phase                            $631,650

Total Estimated Project Cost            $1,136,968

 

Budget Difference                             $152,974

 

Transfer to Storm CIP                       $  152,974

 

 

VI.                     ALTERNATIVES TO STAFF RECOMMENDATION

 

None

 

VII.                     TIME CONSTRAINTS

 

Following project acceptance, in accordance with RCW 60.28, the contract retainage will be released upon receipt from the Washington State Department of Revenue and Labor and Industries, and mandatory 45-Day waiting period for filing claims and liens.   

 

VIII.                     LIST OF ATTACHMENTS

 

Attachment A: Vicinity Map