Title: Approval of a 96-hour Full Closure of the Intersection of NE 24th Street and 152nd Avenue NE for the Construction of 152nd Main Street Project
Attachments: 1. Agenda Memo, 2. Attachment A: Vicinity Map

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Phil Williams

425-556-2880

Planning and Community Development

Carol Helland

425-556-2107

 

DEPARTMENT STAFF:

Public Works

Bassam Al-Ali

Project manager

Planning and Community Development

Peter Dane

Planner-Senior

Public Works

Paul Cho

City Traffic Engineer

 

 

TITLE:

title

Approval of a 96-hour Full Closure of the Intersection of NE 24th Street and 152nd Avenue NE for the Construction of 152nd Main Street Project 

 

OVERVIEW STATEMENT:

recommendation

The 152nd Avenue Main Street project plans to close the intersection of NE 24th Street and 152nd Avenue NE for a maximum of 96 hours during construction to create a new design profile and improvements to the intersection, reduce overall project cost, increase contractor production, and decrease travel impacts on nearby businesses and the community. This closure would be coordinated with other roadway closures in the vicinity to ensure adequate detour routes. Once a contractor has been selected and a project schedule submitted to the city we will develop a detailed public outreach program to notify the public about the closure using a combination of direct mail, project handouts, social media (Facebook, Twitter, City web site), variable-message sign boards, fixed signage, and other approaches. The closer the project gets to executing this requested closure the more comprehensive and detailed that effort will become with the goal being zero surprises.             

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Council approval is required per RMC 10.24.047

                     Required:

N/A

                     Council Request:

N/A

                     Other Key Facts:

The project contract specifications are being finalized in advance of a competitive bidding process. The City will only see the anticipated cost savings from proposed closure if included in the contract documents prior to bid.

OUTCOMES:

Full roadway closure of the NE 24TH Street and 152nd Avenue NE intersection will allow for a safer project work site, less impact to nearby businesses, substantial overall project savings, and will provide a higher overall level of safety to the travelling public.     

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

Estimated August/September 2022: Informing the public, coordination with the City of Bellevue, Microsoft, and nearby businesses.  

                     Outreach Methods and Results:

The community will be notified via traffic alerts through the City traffic map, signage placed during construction directing motorists to a detour route, and messages distributed via the City newsletter and social media prior to closure. Access to residents and businesses will be maintained during the construction phase.

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

This proposal is anticipated to reduce construction phase costs for the 152nd Avenue Main Street project. There is no cost for this request.

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP- Overlake Urban Center Investment (Map#39)

 

Budget Priority:

Vibrant and connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

N/A

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

9/4/2018

Business Meeting

Approve

4/5/2022

Committee of the Whole - Planning and Public Works

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

Council approval is necessary prior to going to bid advertisement in May 2022, for the City to see project cost savings from the proposed road closure. 

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Higher contractor bids and more contract working days resulting in additional impacts to nearby businesses and safety risks to motorized and non- motorized traffic.   

 

 