Legislation Details

File #: AM No. 26-A272 PW/PK   
Type: Consent Item Status: Agenda Ready
File created: 8/25/2026 In control: City Council
On agenda: 9/15/2026 Final action:
Title: Approval of the Final Contract with Integrity Energy Service (IES) and Acceptance of Construction for the Sustainability LED Lighting Retrofit Project
Attachments: 1. Attachment A: Project Information Sheet, 2. Attachment B: Additional Project Information, 3. Attachment C: DES Executed Contract

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Chris Stenger (Interim Director)

425-403-5510

Parks

Loreen Hamilton

425-979-8280

 

DEPARTMENT STAFF:

Public Works

Amy Kim

Capital Project Manager

Public Works

Eric Dawson

Engineering Supervisor

Public Works

Steve Gibbs

Capital Projects Division Manager

Parks

Casey Huebner

Manager

Parks

Danika Globokar

Deputy Director

Executive

Jenny Lybeck

Environmental Sustainability Program Manager

 

 

TITLE:

title

Approval of the Final Contract with Integrity Energy Service (IES) and Acceptance of Construction for the Sustainability LED Lighting Retrofit Project

 

OVERVIEW STATEMENT:

recommendation

Public Works is requesting Council approve the final contract and accept construction for the Sustainability LED Lighting Retrofit project (No. 2340). This contract with IES had a total project cost of $764,062 with savings of $12,156, resulting in a final contract amount of $751,905.

 

This is an Energy Savings Performance Contract (ESPC) project, with the contract administered through the Washington State Department of Enterprise Services (DES). To participate, the local government signs an Interagency Agreement (IAA) with DES. On May 7, 2024, the Council authorized the Mayor to sign an IAA, which the Mayor signed on May 17,2024.

DES formally accepts and administers the ESPC contract and enforces the contractual obligations and requirements on behalf of the City. The project is still being brought to City Council for acceptance as part of the City’s authorization process, while DES has carried out the State-level contract administration and enforcement functions.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Community Strategic Plan

2025 Environmental Sustainability Action Plan

Capital Facilities Plan 2025-30

2021 City Operations Zero Carbon Strategy

Climate Emergency Declaration

                     Required:

Council approval is required to accept a Public Works contract that exceeds $300,000 (2018 City Resolution 1503).

                     Council Request:

N/A

                     Other Key Facts:

Public Works is requesting this item go forward for Council approval at the September 15, 2026, Council business meeting. The project achieved substantial completion on March 23, 2026. DES Substantial Completion/Notice of Completion triggers the start of the one-year Measurement & Verification (M&V) period. During this period, the project’s actual energy performance is measured and verified against the guaranteed energy savings established under the ESPC. DES holds a separate M&V contract to perform this verification, and following completion of the one-year period, the City will receive an updated report documenting the project’s performance and whether the guaranteed energy savings have been achieved.

 

OUTCOMES:

City Hall (107,000 SF) is subject to the Clean Buildings Performance Standard, with a June 1, 2027 compliance deadline for buildings greater than 90,000 SF and less than 220,001 SF. This project enabled the City to meet the applicable requirements ahead of schedule.

 

The project is expected to generate approximately $28,000 in annual utility and operational cost savings, including an estimated reduction of 500 kW in peak demand and 155,000 kWh in annual electricity use.

 

Overall, the lighting upgrade is expected to reduce City Hall’s total utility costs by approximately 9%, primarily through reduced electricity consumption and demand.

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

The project has been featured multiple times in the City’s Redmond Our Stories communications before and during construction. The City is currently working with its Communications team on a new story highlighting the project’s completion and the benefits of the improvements.

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$751,905

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Healthy and Sustainable

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

General Fund

PSE Rebate

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

4/1/2025

Committee of the Whole - Planning and Public Works

Provide Direction

4/15/2025

Business Meeting

Approve

9/1/2026

Committee of the Whole - Planning and Public Works

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

N/A. DES will administer the release of contract retainage in accordance with the ESPC contract and applicable state requirements.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

N/A. The warranty period has begun, and the City will conduct a warranty walk-through prior to the end of the one-year warranty period to identify and address any outstanding issues.

 

 

ATTACHMENTS:

Attachment A: Sustainability LED Lighting Building Retrofit Project Information Sheet

Attachment B: Additional Project Information

Attachment C: DES Executed Contract