City of Redmond Logo
File #: AM No. 23-077   
Type: Consent Item Status: Passed
File created: 5/26/2023 In control: City Council
On agenda: 6/20/2023 Final action: 6/20/2023
Title: Acceptance of the Sound Transit System Access Grant for 156th Ave Cycle Track Project
Attachments: 1. Agenda Memo, 2. Attachment A: Redmond System Access Fund Agreement, 3. Attachment B: CIP Project Information Sheet

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Planning and Community Development

Carol Helland

425-556-2107

 

DEPARTMENT STAFF:

Planning and Community Development

Micah Ross

Senior Engineer

Planning and Community Development

Vangie Garcia

Engineering Manager

Planning and Community Development

Seraphie Allen

Deputy Director

 

 

TITLE:

title

Acceptance of the Sound Transit System Access Grant for 156th Ave Cycle Track Project

 

OVERVIEW STATEMENT:

recommendation

The City has been awarded $1,160,000 through Sound Transit’s System Access Fund competition for the construction phase of the 156th Ave Cycle Track project, which is adjacent to the Redmond Technology Light Rail Station.  Bids for construction of the project were opened on May 25, 2023, and award is on the consent agenda for June 20, 2023.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Transportation Master Plan

                     Required:

Council approval is required for grant acceptance.

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

Grant funds will contribute to the construction of this project, which supports pedestrian and bicycle mobility in the vicinity of the new Redmond Technology Light Rail Station.

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

Grant Funding: $1,160,000

Total Project Cost: $7,659,059

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

000034

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

Sound Transit System Access Grant

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

 

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

6/6/23

Committee of the Whole - Planning and Public Works

Approve

 

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

 

None proposed at this time

N/A

 

Time Constraints:

N/A

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Without the contribution of grant funding the project would require additional local funds to construct.

 

 

ATTACHMENTS:

Attachment A: Grant Funding Agreement

Attachment B: CIP Project Information Sheet