TITLE:
title
Redmond Senior & Community Center Monthly Update
OVERVIEW STATEMENT:
recommendation
Staff will present an update on the Redmond Senior & Community Center project that will include updated timeline for site development (Attachment D), site plans with impacted trees/tree removal as well as mitigation (Attachment C), and Groundbreaking Ceremony plans.
body
☒ Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
☒ Receive Information ☐ Provide Direction ☐ Approve
REQUEST RATIONALE:
• Relevant Plans/Policies:
o Envision Redmond Senior Center Building Stakeholders Report March 2020
o Redmond Community Strategic Plan
o 2017 Community Priorities for the Future of Redmond’s Community Centers Report
o Redmond Comprehensive Plan
o Redmond Parks, Arts, Recreation, Culture, and Conservation (PARCC) Plan
o Redmond Facilities Strategic Management Plan
o 2017-2022 Redmond Capital Investment Program (CIP). Redmond Zoning Code 21.10.070B
• Required:
City Comprehensive Plan: FW-23, CC-12, PR-19, PR-35, PR-36, PR-37, PR-38, UC-19, UC-20, DT-12, and DT-15, Redmond Zoning Code-RZC 21.10.070B
• Council Request:
On July 20, 2021, Council provided direction to proceed with the design and construction of the Redmond Senior & Community Center at a total cost of $44 million. In February 2022, an ordinance was passed increasing this total cost to $48 million.
• Other Key Facts:
N/A
OUTCOMES:
Inform City Council of upcoming site changes and bring back additional information requested.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
• Timeline (previous or planned):
See Attachment A - Community and Stakeholder Outreach and Involvement
• Outreach Methods and Results:
See Attachment A - Community and Stakeholder Outreach and Involvement
• Feedback Summary:
See Attachment A - Community and Stakeholder Outreach and Involvement
BUDGET IMPACT:
Total Cost:
$48 million
Approved in current biennial budget: ☒ Yes ☐ No ☐ N/A
Budget Offer Number:
CIP
Budget Priority:
Infrastructure, Healthy and Sustainable, Vibrant and Connected
Other budget impacts or additional costs: ☐ Yes ☒ No ☐ N/A
If yes, explain:
N/A
Funding source(s):
CIP: $17.116 million
State Capital Adopted Budget: $1.25 million
Surplus Park Impact Fees from 2019-202: $1.648 million
Surplus REET from 2019-2020: $2.486 million
Councilmanic Bonds: $16.0 million
One-time Cash: $9.5 million
Budget/Funding Constraints:
N/A
☐ Additional budget details attached
COUNCIL REVIEW:
Previous Contact(s)
Date |
Meeting |
Requested Action |
N/A |
See Attachment B - Council Review Previous Contacts |
N/A |
Proposed Upcoming Contact(s)
Date |
Meeting |
Requested Action |
5/3/2022 |
Committee of the Whole - Planning and Public Works |
Receive Information |
Time Constraints:
This project continues to run on a tight timeline and we will continue briefing City Council regularly to meet completion at the end of 2023.
ANTICIPATED RESULT IF NOT APPROVED:
N/A
ATTACHMENTS:
Attachment A - Community and Stakeholder Outreach and Involvement
Attachment B - Council Review Previous Contacts
Attachment C - Site Plan with Tree Impact
Attachment D - Timeline for Site Development