Title: First Quarter 2025 Financial Report
Attachments: 1. Agenda Memo, 2. Attachment A: First Quarter 2025 Financial Report Presentation

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Finance

Kelley Cochran

425-556-2748

 

DEPARTMENT STAFF:

Finance

Haritha Narra

Deputy Finance Director

Finance

Hailey Zurcher

Financial Planning Manager

 

 

TITLE:

title

First Quarter 2025 Financial Report

 

OVERVIEW STATEMENT:

recommendation

Review the City's financial performance from January 2025 to March 2025. Please note that the 2024 year-end process is still in progress, and the figures presented here are preliminary due to the impact on January figures.

 

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

N/A

                     Required:

N/A

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

The key financial highlights from January 1, 2025, through March 31, 2025, include the following:

 

REVENUE:

 

Total revenue is 8.9%, or $1.7 million, below target.

                     Property Tax is 96.6%, or $339,000, above target.

 

                     Sales & Use Tax is 54.9% ($1.8 million) above target, driven primarily by growth in wholesale and information industries. Please note that due to a two-month lag in collections, March 2025 is not yet included.

 

                     Utility & Other Taxes are 9.4%, or $230,000, below target.

 

                     Development Permits and Fees are 21.0%, or $844,000, below target, due to a decrease in construction activity compared to previous years. Development fees were updated in 2024.

 

                     Other Revenues are 42.5%, or $2.2 million, below target.

 

EXPENDITURES:

 

                     Total expenditures are 0.6%, or $2.2 million, under target.

 

                     Spend rate for some departments are above/below target:

 

                     Executive Department is 2.5%, or $368,000, below target primarily due to position vacancies.

 

                     Planning Department is 3.0%, or $892,000, below target primarily due to position vacancies and timing of one-time expenditures.

 

                     TIS Department is 1.0%, or $278,000, over the target primarily due to one-time, annual subscription payments paid in January.

 

                     Overtime Expenditures: Total overtime expenditures are 5% (596,000) over the expected target. Overages are primarily seen in the Fire department, due to timing of reimbursable overtime expenditures during the California Wildfire deployment, and the backfilling of department vacancies.

 

                     Capital Investment Program (CIP): Total expenditures are 6.10%, or $10.5 million, under budget, reflecting the continuation of several major projects and the commencement of new initiatives, including the Evans Creek Relocation project, Pedestrian and Bicycle Improvements, Downtown Adaptive Signals, Pavement Repairs, MOC Predesign, and ADA Facility Improvements.

 

                     Business Technology Investment Program (BTIP): Total expenditures are 7.5%, or $711,000, under budget, reflecting the continuation of some major projects and the commencement of new initiatives, including Workforce Management Phase 2, Dynamics 365, and Tourism Data Software Implementation.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

N/A

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

N/A

 

Budget Priority:

Strategic and Responsive

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

N/A

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

N/A

Item has not been presented to Council

N/A

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

N/A

 

 

ANTICIPATED RESULT IF NOT APPROVED:

N/A

 

 

ATTACHMENTS:

Attachment A: First Quarter 2025 Financial Report Presentation