File #: AM No. 23-034   
Type: Consent Item Status: Passed
File created: 2/22/2023 In control: City Council
On agenda: 3/21/2023 Final action: 3/21/2023
Title: Authorize the Mayor or Her Designee to Access Sourcewell Cooperative Purchasing Contract No. 031622-AST for the Purchase and Replacement of Turf at Grass Lawn Park Multi-use Field #2, in the Amount Not-to-Exceed Project Budget of $2,048,633, Project No. 50012206
Attachments: 1. Agenda Memo, 2. Attachment A: Vicinity Map

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Parks

Loreen Hamilton

425-556-2336

 

DEPARTMENT STAFF:

Parks

Dave Tuchek

Deputy Director

Public Works

Jon Spangler

Engineering Manager

Parks

Eric O’Neal

Contract Manager

 

 

TITLE:

title

Authorize the Mayor or Her Designee to Access Sourcewell Cooperative Purchasing Contract No. 031622-AST for the Purchase and Replacement of Turf at Grass Lawn Park Multi-use Field #2, in the Amount Not-to-Exceed Project Budget of $2,048,633, Project No. 50012206

 

OVERVIEW STATEMENT:

recommendation

The synthetic turf on the Multi-use Field #2 at Grass Lawn Park was installed in 2009 and has reached the end of its useful life.  The replacement turf system includes a shock pad and will be the third consecutive turf replacement project to use an alternative to crumb rubber infill.  The playing surface will include lines for soccer, softball and cricket.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

CIP Portfolio Management

PARCC Plan

                     Required:

Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

 

OUTCOMES:

The completion of this project will result in more inclusive recreation facilities for Redmond residents.  The new turf system will provide a safe and consistent playing surface for its entire life expectancy.

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

10/1/2022 through 11/30/2022.  Primary Cricket Field User Groups

                     Outreach Methods and Results:

Direct contact via phone and email.

                     Feedback Summary:

The Cricket user groups provided detailed information on pitch layout and orientation of field lines.  This information was added directly into the design drawings.

 

 

BUDGET IMPACT:

 

Total Cost:

Not-to-Exceed amount of $2,048,633

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP - Project # 50012206.18.01.03

 

Budget Priority:

CIP

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

 

Funding source(s):

CIP

 

Budget/Funding Constraints:

An executed construction contract must be in place by Spring 2023 to allow ample time for the contractor to order materials from their manufacturing suppliers as lead times have become less predictable.

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s) 

Date

Meeting

Requested Action

2/28/2023

Committee of the Whole - Parks and Environmental Sustainability

Approve

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

An executed construction contract must be in place by Spring 2023 to allow ample time for the contractor to order materials from their manufacturing suppliers as lead times have become less predictable.  The construction window for this project is 8/21/2023 through 10/31/2023.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

If this project does not move forward this year, the synthetic turf at Grass Lawn Multi-use Field #2 will continue to degrade.  Increased resources will be required to maintain the field in a minimally safe condition until it reaches the point that requires closure.

 

 

ATTACHMENTS:

Attachment A:  Vicinity Map