File #: AM No. 23-074   
Type: Consent Item Status: Passed
File created: 5/23/2023 In control: City Council
On agenda: 6/20/2023 Final action: 6/20/2023
Title: Approval of the Final Contract with Lakeside Industries, in the Amount of $1,728,760, and Acceptance of Construction for the 90th Street Preservation Project
Attachments: 1. Agenda Memo, 2. Attachment A: 90th Street Preservation Map, 3. Attachment B: Additional Project Information

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

Planning and Community Development

Carol Helland

425-556-2107

 

DEPARTMENT STAFF:

Public Works

Bassam Al-Ali

Senior project manager

Public Works

Adnan Shabir

Senior Engineer

Planning and Community Development

Micah Ross

Senior Engineer

 

 

TITLE:

title

Approval of the Final Contract with Lakeside Industries, in the Amount of $1,728,760, and Acceptance of Construction for the 90th Street Preservation Project

 

OVERVIEW STATEMENT:

This contract with Lakeside Industries for the 90th Street Preservation, Project No. 20012026, had a base bid amount of $1,817,990. Taking into account plus or minus change orders and bid items increases or decreases, the final contract amount is $1,728,760. Staff is also asking Council to accept construction.

 

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

N/A

                     Required:

Council approval is required to accept a Public Works contract that exceeds $300,00 (2018 City Resolution 1503).

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

This project was initiated to address the deteriorating condition of the pavement on NE 90th Street between Redmond-Woodinville Road and Willows Road. The project improved driving safety by a complete pavement resurfacing and new channelization. In addition, safety improvements to the bike lanes were added, including bike detection at signals and green pavement markings to make the separated bike through lane at the NE 161st Ave NE intersection more visible. All curb ramps within the project limits were brought up to current ADA standards and improved pedestrian push button pedestals were installed where required.

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$1,728,760

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

CIP funds and PSRC Federal Grant

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

4/19/2022

Business Meeting

Approve

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

Following project acceptance, in accordance with RCW 60.28, the contract retainage will be released upon receipt of clearances from the Washington State Departments of Revenue and Labor and Industries, and a mandatory 45-day waiting period for filing claims and liens.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

The warranty period begins upon Council acceptance. Not accepting construction will result in the delay of the warranty start, increasing the project close-out cost.

 

 

ATTACHMENTS:

Attachment A: Vicinity Map

Attachment B: Additional Project Information