Title: Pavement Management Program Update
Attachments: 1. Agenda Memo, 2. Attachment B: Pavement Strategic Plan, 3. Attachment C: Implementation Plan, 4. Attachment A- Pavement Program Update
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Adnan Shabir

Senior Engineer

Public Works

Brandon Buehler

Deputy Director

Public Works

Paul Cho

Engineering Manager

Public Works

Patty Criddle

Engineering Supervisor

 

 

TITLE:

title

Pavement Management Program Update

 

OVERVIEW STATEMENT:

recommendation

The pavement strategic plan was completed by Perteet Inc. using a one‑time allocation of $40,000 in the 2025-2026 biennium. The plan uses 2025 pavement condition data, together with historical City pavement data, to model future pavement conditions under various funding scenarios, recommend funding levels aligned with nationally recognized PCI targets, and identify appropriate pavement treatments. The funding strategy to advance the plan will be transmitted with the Mayor's 2027-2028 budget proposal later this year; this study session prepares Council for that conversation.

 

The City has invested steadily in its pavement network over the years. As the network has aged, our overall PCI now stands at 68 (Fair), just short of the Transportation Master Plan's target of 70 and the Pavement Strategic Plan's recommended target of 71. Principal Arterials, our highest-priority corridors, average a PCI of 64, with 38% of those lane-miles in need of attention, representing our biggest opportunity to protect the investment we've already made. Acting now positions the City to achieve the level of service goal of 71 PCI with a long-term goal of 75 PCI.

 

Deferring investment will increase long-term costs. Pavement at a PCI of 55 costs four to six times more to rehabilitate than pavement at PCI 75. The Pavement Management Strategic Plan and accompanying Implementation Plan establish a complete inventory of existing conditions, evaluate future outcomes under various funding scenarios, and provide an actionable roadmap for strategic investments that will preserve the City’s $450 million roadway asset.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Transportation Master Plan; Municipal Asset Management Policy (MAMP); Redmond 2050

                     Required:

N/A

                     Council Request:

N/A

                     Other Key Facts:

The City’s 362 lane-mile street network has a replacement value of ~$450 million. The network PCI has declined from 88 (Good) in 2003 to 68 (Fair) today. The recommended budget scenario of $5 million base plus $250,000 in annual increases beginning in 2027, funded through a dedicated, reliable funding source to be proposed in the Mayor's 2027-2028 budget, is projected to stabilize the network. Leveraging grant funding alongside this base budget is expected to advance the network toward the minimum target PCI of 71 (Satisfactory) by 2039 with a long-term goal of PCI 75. The Implementation Plan also proposes a potential future establishment of a dedicated in-house paving crew, separate from CIP, to deliver preventive maintenance and residential rehabilitation work beginning in 2027. An in-house paving crew can also be used to complete targeted treatments to improve PCI to a degree that may increase a project’s eligibility for grant funding.

 

 

OUTCOMES:

 

The Pavement Strategic Plan and Implementation Plan together provide clear guidance on the investments required for long-term pavement preservation. The main elements of the plans include:

 

                     Current state of the City’s pavement: network PCI of 68 (Fair), down from 88 (Good) in 2003; 38% of Principal Arterial lane-miles in Poor or worse condition; 49% of the network in Satisfactory or better condition.

                     Recommended budget to achieve a target PCI of 71: $5 million base budget starting in 2027, increasing by $250,000 annually, funded through the Transportation Benefit District or another reliable funding source; with an initial focus on arterial rehabilitation.

                     Pavement treatment strategy: data-driven treatment selection by functional class and PCI condition, shifting from reactive “worst-first” repairs to lifecycle-based preventive maintenance; preventive treatments cost four to six times less than rehabilitation.

                     Resource needs to achieve target levels: Biannual reporting and continued condition assessments to assess progress toward PCI 71, and potential future establishment of a City paving crew.

 

 

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

Public Works presented an update of the pavement management program to the Council at a Study session on May 10th, 2022.

Transportation Planning also conducted outreach as part of the Transportation Master Plan update that includes a section on pavement management.

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

No impact to the current biennium budget. The proposed $5 million base programmatic paving budget would begin in the 2027-2028 biennium. By 2039 the annual paving budget would be $8 million due to the proposed annual increase of $250,000. 

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

N/A

 

Budget Priority:

N/A

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

Examples: software with a yearly cost, revenue generating, match requirements, etc. - if none, enter N/A.

 

Funding source(s):

Transportation Benefit District or another reliable funding source

 

Budget/Funding Constraints:

None

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

N/A

Item has not been presented to Council

N/A

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

7/14/2026

Study Session

Receive Information

 

Time Constraints:

Public Works target for completing and presenting the Pavement Management Strategic Plan and Implementation Plan in July 2026. Council adoption of the recommended budget scenario is needed by Q3-Q4 2026 to enable the 2027 program launch.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

The recommended investment is timely and cost-effective. In the absence of a dedicated, sustained paving budget, the network's overall condition is projected to decline to Poor (PCI below 55) within seven years. At that threshold, preventive preservation treatments are no longer viable, and the City would be limited to substantially more expensive rehabilitation and reconstruction. Because pavement at PCI 55 costs four to six times more to restore than pavement maintained at PCI 75, a consistent annual investment maximizes the return on every dollar and protects the long-term value of our roadway asset. Sustained funding also maintains the safety, ride quality, and environmental performance that residents and businesses rely on.

 

 

ATTACHMENTS:

Attachment A: Pavement Program Update

Attachment B: Pavement Strategic Plan

Attachment C: Implementation Plan