File #: CM 26-052   
Type: Committee Memo Status: Referred
File created: 1/26/2026 In control: City Council
On agenda: 2/17/2026 Final action:
Title: Accept Funds and Add Overlake Area Bicycle/Pedestrian Improvements Project to CIP
Attachments: 1. Agenda Memo, 2. Attachment A: Funding Award Letter, 3. Attachment B: Vicinity Map

TO: Committee of the Whole - Planning and Public Works

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Planning and Community Development

Carol Helland

425-556-2107

 

DEPARTMENT STAFF:

Planning and Community Development

Seraphie Allen

Deputy Director

Planning and Community Development

Michael Hintze

Transportation Planning Manager

Planning and Community Development

Micah Ross

Senior Engineer

 

 

TITLE:

title

Accept Funds and Add Overlake Area Bicycle/Pedestrian Improvements Project to CIP

 

OVERVIEW STATEMENT:

recommendation

WSDOT has awarded the City $8,000,000 in Move Ahead Washington (MAWA) funds for the Overlake Area Bicycle/Pedestrian Improvements Project.  This project will construct a shared use path on 148th Ave from NE 31st St to NE 40th Street, and bike lanes on NE 36th Street from 148th Ave to the 520 Trail (the scope of this project was previously for the construction of a new pedestrian bridge over Hwy 520 along 148th Ave, titled 148th Ave Trail - 520 to NE 24th St).  This request is to accept funds from WSDOT and add the project into the City’s Capital Investment Program.

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Capital Investment Program (CIP), Transportation Master Plan (TMP)

                     Required:

Council approval is required to accept grant funding

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

Design and construction of this project supports safe pedestrian and bicycle movement on key north/south and east/west corridors in the Overlake area as identified in the Transportation Master Plan.

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

Outreach will be included in the project’s design phase.

                     Outreach Methods and Results:

Anticipated outreach will include website updates, post card mailer, open house, and direct outreach.

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

Total: $8,000,000

*$3,000,000 of the total funding is designated for the 2027-2029 biennium, and will require Legislative action prior to authorization.

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

No additional dollars are being requested. This is reflective of a change of scope for the project.

 

Budget Offer Number:

0000384 - Transportation Capital CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

Annual operations and maintenance costs after the project is completed.

 

Funding source(s):

Grant - Move Ahead Washington (MAWA)

 

Budget/Funding Constraints:

Funding must be obligated during the biennium to maintain funding and project status.

 

  Additional budget details attached

 

 

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

N/A

Item has not been presented to Council

N/A

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

2/17/2026

Business Meeting

Approve

 

Time Constraints:

Funds are currently available to be obligated

 

 

ANTICIPATED RESULT IF NOT APPROVED:

State funding would be returned.

 

 

ATTACHMENTS:

Attachment A: Funding Award Letter

Attachment B: Vicinity Map