File #: AM No. 23-096   
Type: Consent Item Status: Passed
File created: 6/14/2023 In control: City Council
On agenda: 7/18/2023 Final action: 7/18/2023
Title: Approval of the Sourcewell Cooperative Purchasing Contract for the Perrigo Park Field Lighting Energy Efficiency Conversion
Attachments: 1. Agenda Memo, 2. Attachment A: Vicinity Map

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Parks

Loreen Hamilton

425-556-2336

 

DEPARTMENT STAFF:

Parks

Dave Tuchek

Deputy Director

Public Works

Jon Spangler

City Engineer

Parks

Eric O’Neal

Contract Manager

 

 

TITLE:

title

Approval of the Sourcewell Cooperative Purchasing Contract for the Perrigo Park Field Lighting Energy Efficiency Conversion

OVERVIEW STATEMENT:

recommendation

 The original field lighting system at Perrigo Park is 20 years old and uses inefficient lighting technology to illuminate the sports field and surrounding areas.  The LED replacement fixtures will reduce energy consumption by more than 50% and will decrease ongoing maintenance requirements.  This will be the fourth energy efficient sports field light conversion project for the City of Redmond.  The action to be requested will be to authorize the Mayor or Her Designee to Access a Sourcewell Cooperative Purchasing Contract for the Perrigo Park Field Lighting Energy Efficiency Conversion, in the Amount Not-to-Exceed Project Budget of $951,567, Project No. 20022334.07.01.00    

 

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

CIP Portfolio Management

PARCC Plan

Environmental Sustainability Action Plan

                     Required:

Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

This project will help move the City of Redmond closer to its carbon neutrality goals.  The new LED fixtures require less ongoing maintenance and greatly reduce the amount of light spill into the night sky.  Customers will experience more consistent illumination of the sports surface with the new lighting technology.

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

9/1/23 through 10/31/23

                     Outreach Methods and Results:

o                     Direct contact with user groups regarding potential construction impacts. 

o                     Social media project updates to keep the community informed. 

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

Not-to-Exceed Project Budget of $951,567

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP - Project # 20022334.07.01.00

 

Budget Priority:

Healthy and Sustainable

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

CIP

 

Budget/Funding Constraints:

An executed contract by 8/27/23 will result in an estimated 3% in project savings.  New cooperative purchasing rates will increase after this date.  Construction is to occur in November and December of 2023.

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

6/27/2023

Committee of the Whole - Parks and Environmental Sustainability

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

If delayed until later in the biennium this project will incur increased lighting equipment costs, increased energy costs and increased maintenance costs.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

If not approved the existing lighting system will be maintained at higher operating costs and will not move the City of Redmond closer to its carbon neutrality goals.

 

 

ATTACHMENTS:

Attachment A:  Vicinity Map