TO: Committee of the Whole - Parks and Environmental Sustainability
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Parks |
Loreen Hamilton |
425-556-2336 |
Public Works |
Aaron Bert |
425-556-2786 |
DEPARTMENT STAFF:
Public Works |
Eric Dawson |
Senior Engineer |
Parks |
Zach Houvener |
Deputy Director |
TITLE:
title
Redmond Senior & Community Center Operational Update
OVERVIEW STATEMENT:
recommendation
Staff will present a programmatic update on the Redmond Senior & Community Center project including program planning, operations, staffing, and Grand Opening information.
body
☐ Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
☒ Receive Information ☐ Provide Direction ☐ Approve
REQUEST RATIONALE:
• Relevant Plans/Policies:
o Envision Redmond Senior Center Building Stakeholders Report March 2020
o Redmond Community Strategic Plan
o 2017 Community Priorities for the Future of Redmond’s Community Centers Report
o Redmond Comprehensive Plan
o Redmond Parks, Arts, Recreation, Culture, and Conservation (PARCC) Plan
o Redmond Facilities Strategic Management Plan
o 2017-2022 Redmond Capital Investment Program (CIP). Redmond Zoning Code 21.10.070B
• Required:
City Comprehensive Plan: FW-23, CC-12, PR-19, PR-35, PR-36, PR-37, PR-38, UC-19, UC-20, DT-12, and DT-15, Redmond Zoning Code-RZC 21.10.070B
• Council Request:
On July 20, 2021, Council provided direction to proceed with the design and construction of the Redmond Senior & Community Center at a total cost of $44 million. The current budget of $61.7 million was approved in February 2024.
• Other Key Facts:
N/A
OUTCOMES:
Inform City Council on the progress of planning for opening and operations of the Redmond Senior & Community Center.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
• Timeline (previous or planned):
See Attachment A
• Outreach Methods and Results:
See Attachment A
• Feedback Summary:
See Attachment A
BUDGET IMPACT:
Total Cost:
$61.7 million
Approved in current biennial budget: ☒ Yes ☐ No ☐ N/A
Budget Offer Number:
CIP
Budget Priority:
Infrastructure, Healthy and Sustainable, Vibrant and Connected
Other budget impacts or additional costs: ☐ Yes ☒ No ☐ N/A
If yes, explain:
N/A
Funding source(s):
CIP - $187,000
General Fund Surplus - $13.465 million
Park Impact Fees - $14.498 million
REET - $15.800 million
Councilmanic Bonds - $16 million
King County Parks Levy Grant - $500,000
State Capital Grant - $1.25 million
Budget/Funding Constraints:
N/A
☐ Additional budget details attached
COUNCIL REVIEW:
Previous Contact(s)
Date |
Meeting |
Requested Action |
See Attachment B |
N/A |
N/A |
Proposed Upcoming Contact(s)
Date |
Meeting |
Requested Action |
N/A |
None proposed at this time |
N/A |
Time Constraints:
This project continues to run on a tight timeline and will continue briefing City Council regularly.
ANTICIPATED RESULT IF NOT APPROVED:
N/A
ATTACHMENTS:
Attachment A - Outreach & Stakeholder Engagement
Attachment B - Previous City Council Contacts