TO: Committee of the Whole - Parks and Environmental Sustainability

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Parks

Loreen Hamilton

425-556-2336

 

DEPARTMENT STAFF:

Parks

Caroline Chapman

Parks Planning Manager

Parks

Cameron Zapata

Senior Planner

 

 

TITLE:

title

Southeast Redmond Neighborhood Park Master Plan Update

 

OVERVIEW STATEMENT:

recommendation

As part of the approved 2023-24 budget, Berger Consulting will lead the SE Redmond Neighborhood Park Master Plan project. The Master Plan will be developed in coordination with community outreach; the Parks, Trails, and Recreation Commission; and staff feedback. Staff will present an update on the project and summary of community feedback received to date. 

body

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

2023/24 City of Redmond Adopted Budget

2017 PARCC Plan

                     Required:

N/A

                     Council Request:

N/A

                     Other Key Facts:

$75,000 was allocated for this project in the 2023/24 adopted budget.

 

 

OUTCOMES:

Developing a Southeast Redmond Neighborhood Park Master Plan will help define community needs and support the future funding, design, and construction of the park

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

Fall 2023: Community meetings and public involvement on initial ideas for the park space

Winter 2023: Refinement of conceptual plans for the neighborhood park

 

                     Outreach Methods and Results:

Community meetings (September 13; October 17)

Online questionnaire at LetsConnectRedmond.com/SERedmondPark

Onsite activation and engagement opportunities

 

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$75,000

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

000009 - Parks, Trails, and Open Space and 0000146 - Service Enhancement

 

Budget Priority:

Healthy and Sustainable

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

General Fund Surplus

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

4/25/2023

Committee of the Whole - Parks and Environmental Sustainability

Receive Information

5/2/2023

Business Meeting

Approve

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

10/17/2023

Business Meeting

Provide Direction

1/9/2024

Study Session

Receive Information

 

Time Constraints:

N/A

 

 

ANTICIPATED RESULT IF NOT APPROVED:

This is an area of high need for public park space and is not meeting level of service goals.  If not approved, the timeline to develop and construct a park in SE Redmond will be pushed further out.

 

 

 

ATTACHMENTS:

A.                     Public Outreach Plan

B.                     Kid’s Engagement Sheet