City of Redmond Logo
File #: AM No. 25-056   
Type: Consent Item Status: Passed
File created: 3/25/2025 In control: City Council
On agenda: 4/15/2025 Final action: 4/15/2025
Title: Approval of a Supplemental Construction Agreement with McKinstry Essention, for the Public Safety Building Phase 2 and Sustainability Building Automation Projects, in the Amount of $3,220,000
Attachments: 1. Agenda Memo, 2. Attachment A: Project Information Sheet, 3. Attachment B: Additional Project Information, 4. Attachment C: Investment Grade Audit Report, 5. Attachment D: Energy Service Proposal, 6. Attachment E: Interagency Agreement Amendment No.2, 7. Attachment F: DES Funding Authorization Form

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

Executive

Lisa Maher

425-556-2427

Parks

Loreen Hamilton

425-556-2336

 

DEPARTMENT STAFF:

Public Works

Amy Kim

Engineer

Public Works

Eric Dawson

Engineering Supervisor

Parks

Quinn Kuhnhausen

Parks Manager

Parks

David Tuchek

Parks Deputy Director

Executive

Jenny Lybeck

Environmental Sustainability Program Manager

Public Works

Steve Gibbs

Capital Projects Division Manager

Public Works

Vangie Garcia

Deputy Public Works Director

 

 

TITLE:

title

Approval of a Supplemental Construction Agreement with McKinstry Essention, for the Public Safety Building Phase 2 and Sustainability Building Automation Projects, in the Amount of $3,220,000

 

OVERVIEW STATEMENT:

recommendation

Public Works is requesting to move forward with the next step of the Energy Savings Performance Contract (ESPC) project for the Public Safety Building which is to execute the remaining design and construction.  This contract awards McKinstry Essention $3,220,000 for both the Public Safety Building Phase 2 and Sustainability Building Automation Projects. This effort combines two CIP projects so the budgets have been combined to streamline administration and maximize efficiency. The scope has been optimized to meet state law energy reduction targets while staying under budget and maximizing resources for required energy savings.

The Council previously approved the Interagency Agreement (IAA) with the Washington State Department of Enterprise Services (DES) and an Audit Agreement with McKinstry in 2024. The Investment Grade Audit provided the findings that helped guide proposed improvements that would maximize the available budget while reducing energy consumption and ensuring compliance with the Washington State Clean Buildings Performance Standard.

Further budget and recommended scope information are available in Attachment B, Additional Project Information, and Attachment D, Energy Service Proposal.

body

  Additional Background Information/Description of Proposal Attached

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Community Strategic Plan - Objective #1: Invest in infrastructure preservation and replacement across the City to maintain the current level of service, the reliability of capital assets, and provide timely and cost-effective replacement.

 

2020 Environmental Sustainability Action Plan - Strategy B2: Advance Green Building within City Facilities, and Action B2.2: Energy and Water Retrofits for City Facilities.

 

Capital Facilities Plan 2025-30, 2021 City Operations Zero Carbon Strategy, Climate Emergency Declaration

                     Required:

Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

                     Compliance with the Washington State Clean Building Performance Standard (CBPS) and avoid a penalty of $58,328 per year if not in compliance by the established Tier 1 compliance date, June 1, 2027 (for facilities >50,000 SF but less than 90,001 SF).

                     Reduced utility expenses and decreased maintenance costs associated with emergency equipment replacement.

                     Decreased emissions from buildings by reducing overall energy consumption.

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

The City of Redmond Police Station is a highly secure facility essential to public safety operations. While not open to the public, it serves as the headquarters for the Redmond Police Department and houses critical infrastructure vital to emergency response and law enforcement.

This facility includes secured spaces for police operations, evidence storage, and administrative functions. In addition, it houses a regional NORCOM 911 center, which provides emergency dispatch services to multiple communities and ensures rapid coordination of law enforcement, fire, and medical response. Any disruptions to its operations could impact critical response times and community security.

Extensive planning and coordination have taken place to assess and minimize project impacts. The Police Department has been regularly engaged through intentional coordination efforts, ensuring they are informed and involved in decision-making.

A Police Representative has been invited to bi-weekly project meetings, with additional meetings focused on project schedules, site access, and visits. Beyond these broader discussions, internal meetings have provided deeper engagement to proactively identify sensitive areas and overlapping construction projects within the space. These efforts have helped minimize disruptions and ensure a well-coordinated approach to project execution.

                     Outreach Methods and Results:

Outreach efforts have included larger team meetings, internal discussions, site visits, and walkthroughs with potential contractors and subcontractors. These discussions have influenced scheduling decisions, such as incorporating double shifts or evening work in sensitive areas. Additionally, a liquidated damages clause has been included specifically for the construction of the 911 center to ensure accountability and minimize disruptions.

                     Feedback Summary:

We have developed a more efficient schedule while staying within the original budget and scope. The Police Department appreciated the extra attention given to the 911 area, ensuring minimal disruption to critical operations.

 

BUDGET IMPACT:

 

Total Cost:

$3,220,000

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

Healthy and Sustainable

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

General Fund

Real Estate Excise Tax

Transportation CIP

Grants

Budget/Funding Constraints:

The Association of Washington Cities (AWC) and the WA State Department of Commerce have awarded grants of $72,500 and $26,500, respectively, to reimburse the audit fee for this project. Both grants must be reimbursed by June 13, 2025.

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

4/23/2024

Committee of the Whole - Parks and Environmental Sustainability

Provide Direction

5/7/2024

Business Meeting

Approve

9/3/2024

Committee of the Whole - Planning and Public Works

Provide Direction

9/17/2024

Business Meeting

Approve

4/1/2025

Committee of the Whole - Planning and Public Works

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

This CBPS compliance deadline of June 1, 2028, requires a minimum of 1 year of measurement and verification of the building's energy use. Therefore, considering the commissioning period of the HVAC equipment and building control system, the construction must be completed at least 15 months before the published deadline. In summary, this project must be completed by Q1 2027, and construction should start no later than Q2 2026.  

 

 

ANTICIPATED RESULT IF NOT APPROVED:

If the agreement is not approved, staff would pursue a design-bid-build process which would extend the project schedule. This could lead to a potential violation of State law, CBPS. Failure to submit appropriate documentation by the scheduled reporting date will result in progressive penalties by legal notice.

 

 

ATTACHMENTS:

Attachment A - Project Information Sheet

Attachment B - Additional Project Information

Attachment C - Investment Grade Audit Report

Attachment D - Energy Service Proposal

Attachment E - Interagency Agreement Amendment No.2

Attachment F - DES Funding Authorization Form