File #: AM No. 23-098   
Type: Consent Item Status: Passed
File created: 7/3/2023 In control: City Council
On agenda: 7/18/2023 Final action: 7/18/2023
Title: Award of Bid to HM Pacific Northwest, Inc of Redmond, WA, in the Amount of $1,183,664 for the Avondale Road Preservation Project
Attachments: 1. Agenda Memo, 2. Attachment A: Avondale Preservation Vicinity Map, 3. Attachment B: Additional Project Information

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Public Works

Aaron Bert

425-556-2786

 

DEPARTMENT STAFF:

Public Works

Joseph O’Leary

Senior Project Manager

 

 

TITLE:

title

Award of Bid to HM Pacific Northwest, Inc of Redmond, WA, in the Amount of $1,183,664 for the Avondale Road Preservation Project

 

OVERVIEW STATEMENT:

recommendation

This contract with HM Pacific Northwest in the amount of $1,183,664 is for construction of the Avondale Road Preservation project, Project No. 2120-096-02 (20012120).

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

N/A

                     Required:

Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

The project will repave approximately 2,240 feet of Avondale Road, improving driving safety. In addition, curb ramps within the project limits will be brought up to current ADA standards. Existing bike lanes will be expanded to provide buffered bike lanes, increasing safety for bikers on this busy corridor.

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

N/A

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

$1,183,664

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

CIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

N/A

 

Funding source(s):

General Fund, Real Estate Excise Tax, Federal Grant, Business Tax

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

N/A

Item has not been presented to Council

N/A

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

Award of bid must occur within 45 days of the bid opening (which occurred on June 29, 2023) or the contractor may withdraw their bid. If not approved, City may lose federal funding for this project.

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Not approving contract will result in delaying construction, increasing the cost to complete the project.

 

 

ATTACHMENTS:

Attachment A - Vicinity Map

Attachment B - Additional Project Information