Title: Approval of the CIP Project and Portfolio Management Software Contract with Aurigo Software Services, LLC for the Implementation of Masterworks, in the Amount of $487,366
Attachments: 1. Agenda Memo, 2. Attachment A: Information Privacy and Security Agreement (IPSA), 3. Attachment B: Aurigo Master Service Agreement (MSA), 4. Attachment C: Schedule B - Statement of Work, 5. Attachment D: RFP Attachment A - Key Requirements and Pricing Estimates, 6. Attachment E: Aurigo Service Subscription Agreement (SSA)

TO: Members of the City Council

FROM: Mayor Angela Birney

DEPARTMENT DIRECTOR CONTACT(S):

Technology and Information Services

Michael Marchand

425-556-2173

 

DEPARTMENT STAFF:

Technology and Information Services

Maria O’Neill

Technology Project Manager

 

 

TITLE:

title

Approval of the CIP Project and Portfolio Management Software Contract with Aurigo Software Services, LLC for the Implementation of Masterworks, in the Amount of $487,366

 

OVERVIEW STATEMENT:

recommendation

In the 2023-2024 BTIP, Public Works requested a Capital Investment Program (CIP)- Project and Portfolio Management Tool for managing the documentation, workflow, status and reporting on all aspects of CIP projects. Through a competitive, cross department RFP process, the City has selected Masterworks by Aurigo Software Services, LLC. 

body

  Additional Background Information/Description of Proposal Attached

 

 

REQUESTED ACTION:

 

  Receive Information                                            Provide Direction                                            Approve

 

 

REQUEST RATIONALE:

 

                     Relevant Plans/Policies:

Budget for this project is in the 2023-2024 BTIP

                     Required:

Council approval is required to award a contract that exceeds $50,000

                     Council Request:

N/A

                     Other Key Facts:

N/A

 

 

OUTCOMES:

Improve predictability and consistency in delivery and management of CIP projects by automating processes and centralizing project records, as well as increasing the accuracy and visibility of CIP data.

 

 

 

 

COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

 

                     Timeline (previous or planned):

Estimated implementation timeline is 9 months from contract execution

                     Outreach Methods and Results:

N/A

                     Feedback Summary:

N/A

 

 

BUDGET IMPACT:

 

Total Cost:

The cost for Implementation ($180,052) and the first two years of licensing and support ($307,314) totals $487,366. Implementation fees include professional services for configuration, data migration discovery, and integrations and will be invoiced according to the billing milestones identified in the statement of work. The first year of licensing and support fees will be invoiced beginning when the contract is fully executed and annually on the anniversary of that date.

 

A change order for integrations still in discovery is expected for this project.

 

Approved in current biennial budget:                                            Yes                                            No                                            N/A

 

Budget Offer Number:

BTIP

 

Budget Priority:

Vibrant and Connected

 

Other budget impacts or additional costs:                       Yes                                            No                                            N/A

If yes, explain:

Annual licensing and support fees of $151,386 plus 3% yearly increase

 

Funding source(s):

BTIP Funds

 

Budget/Funding Constraints:

N/A

 

  Additional budget details attached

 

COUNCIL REVIEW:

 

Previous Contact(s)

Date

Meeting

Requested Action

9/10/2024

Committee of the Whole - Finance, Administration, and Communications

Provide Direction

 

Proposed Upcoming Contact(s)

Date

Meeting

Requested Action

N/A

None proposed at this time

N/A

 

Time Constraints:

N/A

 

 

ANTICIPATED RESULT IF NOT APPROVED:

Public Works staff will continue to use manual processes to collect and distribute project information.

 

 

ATTACHMENTS:

Attachment A: Information Privacy and Security Agreement (IPSA)

Attachment B: Aurigo Master Service Agreement (MSA)

Attachment C: Schedule B - Statement of Work

Attachment D: RFP Attachment A - Key Requirements and Pricing

Attachment E: Aurigo Service Subscription Agreement (SSA)