File #: AM No. 23-133   
Type: Consent Item Status: Passed
File created: 8/23/2023 In control: City Council
On agenda: 10/3/2023 Final action: 10/3/2023
Title: Approval of Final Contract with CDK Construction Services in the Amount of $728,998 and Accept Construction for the MOC Plumbing & ADA Improvements Project
Attachments: 1. Agenda Memo, 2. Attachment A: MOC Plumbing & ADA Project Information Sheet, 3. Attachment B: Additional Project Information
TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786

DEPARTMENT STAFF:
Public Works
John Mork
Senior Project Manager


TITLE:
title
Approval of Final Contract with CDK Construction Services in the Amount of $728,998 and Accept Construction for the MOC Plumbing & ADA Improvements Project


OVERVIEW STATEMENT:
recommendation
Staff is requesting that Council approve the final contract and accept construction for the MOC Plumbing & ADA Improvements Project (No. 2107-319-03). This contract with CDK Construction Services had a base bid amount of $720,195, plus, or minus change orders and bid items increases or decreases, resulting in a final contract amount of $728,998.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
N/A
* Required:
Council approval is required to accept a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)
* Council Request:
N/A
* Other Key Facts:
N/A


OUTCOMES:
The Redmond Maintenance and Operation Center (MOC) Building 1 restrooms and locker rooms have been upgraded to address plumbing, ADA, and functional issues.



COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

* Timeline (previous or planned):
N/A
* Outreach Methods and Results:
N/A
* Feedback Summary:
N/A


BUDGET IMPACT:

Total Cost:
$728,998

Approved in current biennial budget: ? Yes ? No ? N/A

Budget Offer Number:
CIP

Budget Priority:
Vibrant and Connected

Other budget impacts or additional costs: ? Yes ? No ? N/A
If yes, explain:
N/A

Funding source(s):
General Fund, Real Estate Excise Tax, Stormwater CIP, Water CIP, Wastewater CIP

Budget/Funding Constraints:
N/A

? Additional budget details attached


COUNCIL REVIEW:

Previous Contact(s)
Date
Meeting
Requested Action
7/19/2022
Business Meeting
Approve

Proposed U...

Click here for full text