TO: Committee of the Whole - Planning and Public Works
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786
DEPARTMENT STAFF:
Public Works
Aaron Noble
Project Manger
Planning and Community Development
Micah Ross
Senior Planner
Public Works
Steve Gibbs
Division Manager
Public Works
Brandon Buehler
Acting Deputy Director
TITLE:
title
Award Construction Contract to NPM Construction of Maple Valley, WA in the Amount of $602,756.50 and Approve Consultant Services Agreement Supplement 07 with Perteet in the Amount of $47,156 for the NE 70th Shared Use Path Project
OVERVIEW STATEMENT:
recommendation
Construct a Shared-use pedestrian and bicycle path in the in the right-of-way of NE 70th with a 12-foot concrete path from Redmond Way to 180th Ave NE. Upgrades will include new crosswalk and intersection improvements at 70th and Redmond Way.
body
? Additional Background Information/Description of Proposal Attached
REQUESTED ACTION:
? Receive Information ? Provide Direction ? Approve
REQUEST RATIONALE:
* Relevant Plans/Policies:
Transportation Master Plan
* Required:
Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503)
* Council Request:
N/A
* Other Key Facts:
Public Works is requesting this item go forward for Council approval at the June 23, 2026, Council business meeting.
OUTCOMES:
This project will complete the shared use path installed NE 70th Street between SR 202 and 180th Ave NE. The project will increase safety by installing bike lanes, bike signal improvements, and lighting along the shared-use path.
COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:
* Timeline (previous or planned):
N/A
* Outreach Methods and Results:
N/A
* Feedback Summary:
N/A
BUDGET IMPACT:
Total Cost:
$3,116,863
Approved in current biennial budget: ? Yes ? No ? N/A
Budget Offer Number:
CIP
Budget Priority:
Vibrant and Connected
Other budget impacts...