File #: AM No. 25-032   
Type: Consent Item Status: Passed
File created: 2/26/2025 In control: City Council
On agenda: 3/18/2025 Final action: 3/18/2025
Title: Approval of a Consultant Agreement with KPFF for Engineering Services for the 156th Ave Shared Use Path Project, in an Amount Not to Exceed $900,000
Attachments: 1. Agenda Memo, 2. Attachment A: Project Information Sheet, 3. Attachment B: KPFF Consultant Agreement
TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Planning and Community Development
Carol Helland
425-556-2107

DEPARTMENT STAFF:
Planning and Community Development
Seraphie Allen
Deputy Director
Planning and Community Development
Michael Hintze
Transportation Planning Manger
Planning and Community Development
Micah Ross
Senior Engineer
Public Works
Rob Crittenden
Senior Engineer


TITLE:
title
Approval of a Consultant Agreement with KPFF for Engineering Services for the 156th Ave Shared Use Path Project, in an Amount Not to Exceed $900,000


OVERVIEW STATEMENT:
recommendation
KPFF has been selected to perform design engineering services for the 156th Ave Shared Use Path project (4300 Block to NE 51st Street). The total contract is not to exceed $900,000. Staff are requesting approval for the Mayor to sign the consultant agreement, and approval to secure right-of-way and/or easements to construct and maintain the improvements.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
Capital Investment Program (CIP), Transportation Master Plan (TMP)
* Required:
RCW 39.80 and City Purchasing Policies and Procedures require Council authorization for the Mayor to sign the contract.
* Council Request:
N/A
* Other Key Facts:
N/A
OUTCOMES:
Design and construction of this project supports pedestrian and bicycle movement on this key north/south corridor, connection non-motorized users to the light rail and beyond.


COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

* Timeline (previous or planned):
Community engagement will take place during the design.
* Outreach Methods and Results:
Outreach will include at a minimum, website updates, post card mailer, and open house.
* Feedback Summary:
N/A


BUDGET IMPACT:

Total Cost:
Project Total: $4,970,518
Design Phase Total: $859,266...