File #: SS 23-034   
Type: Study Session Status: Agenda Ready
File created: 5/26/2023 In control: City Council Study Session
On agenda: 8/8/2023 Final action:
Title: Consultant Agreement with HDR for the NE 95th Street Bridge Replacement Project
Attachments: 1. Agenda Memo, 2. Attachment A: Vicinity Map, 3. Attachment B: Additional Background Information, 4. Attachment C: Consultant Services Agreement
TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786

DEPARTMENT STAFF:
Public Works
Rob Crittenden
Project Manager
Public Works
Patty Criddle
Engineering Supervisor
Public Works
Emily Flanagan
Senior Engineer
Public Works
Jon Spangler
City Engineer


TITLE:
title
Consultant Agreement with HDR for the NE 95th Street Bridge Replacement Project


OVERVIEW STATEMENT:
recommendation
This consultant agreement with HDR in the amount of $430,000 is for survey, hydraulic modeling, geotechnical assessment, a conceptual design report, and initial consultation with outside agencies and tribes to support the development of a preliminary (5% level) design for the replacement of the existing bridge with a pedestrian and bicycle only bridge and the identification of associated environmental mitigation for the NE 95th Street Bridge Replacement project, Project No. 20021406.

Staff is also seeking authorization to contact property owners adjacent to the project to negotiate and acquire right-of-entry permissions for the purposes of tree inventory and land survey.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
N/A
* Required:
Council approval is required to award an Architectural and Engineering Services agreement that exceeds $50,000 (2018 City Resolution 1503)
* Council Request:
N/A
* Other Key Facts:
N/A


OUTCOMES:
The proposed project will remove the existing NE 95th Street vehicular bridge and replace it with a new prefabricated pedestrian and bicycle only bridge that meets current bridge design standards and addresses hydraulic and environmental requirements to cross Bear Creek.


COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

* Timeline (previous or planned):
N/A
* Outreach Methods and Results:
N/A
* Feedback Summary:
N/A


BUDGET IMP...