Title: Approve Final Contract with Rodarte Construction, Inc. of Auburn, WA and Accept Construction for the Hardscape Project - Grass Lawn Park Parking Lot and Increase the Total Funding for this Project
Attachments: 1. Agenda Memo, 2. Attachment A: Hardscape Project Grass Lawn Parking Lot Project Information Sheet, 3. Attachment B: Additional Project Information
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Committee of the Whole - Planning and Public Works
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786

DEPARTMENT STAFF:
Public Works
Joe Averill
Project Manager
Parks
Darcey Rayner-Shepard
Parks Manager
Public Works
Steve Gibbs
Capital Projects Division Manager


TITLE:
title
Approve Final Contract with Rodarte Construction, Inc. of Auburn, WA and Accept Construction for the Hardscape Project - Grass Lawn Park Parking Lot and Increase the Total Funding for this Project


OVERVIEW STATEMENT:
recommendation
Public Works is requesting Council to approve the final contract and accept construction for the Hardscape Project - Grass Lawn Park Parking Lot project No.2322. This contract with Rodarte Construction, Inc. had a base bid amount of $871,256, plus or minus change orders and bid item increases or decreases, resulting in a final contract amount of $899,199.

body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
PARCC Plan, ADA Transition Plan
* Required:
Council approval is required to accept a Public Works contract that exceeds $300,000 (2018 City Resolution 1503).
* Council Request:
NA
* Other Key Facts:
Public Works is requesting this item go forward for Council approval at the March 17, 2026, Council business meeting.


OUTCOMES:
Project objectives included renovation of the Grass Lawn Park parking lot adjacent to 148th Avenue NE
to ensure a safe, level surface for vehicles and park visitors. All project objectives were met.


COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

* Timeline (previous or planned):
N/A
* Outreach Methods and Results:
N/A
* Feedback Summary:
N/A


BUDGET IMPACT:

Total Cost:
$899,199

Approved in current biennial budget: ? Yes ? No ? N/A

Budget Offer Number:
CIP

Budget Priority:
Vibrant and Connected

Other budget impa...