File #: AM No. 25-102   
Type: Consent Item Status: Agenda Ready
File created: 6/9/2025 In control: City Council
On agenda: 7/15/2025 Final action:
Title: Award Construction Contract to A1 Landscaping of Snohomish, WA, in the Amount of $2,739,391, for the Bel-Red Buffered Bike Lanes Project
Attachments: 1. Agenda Memo, 2. Attachment A: Project Information Sheet, 3. Attachment B: Additional Project Information
TO: Members of the City Council
FROM: Mayor Angela Birney
DEPARTMENT DIRECTOR CONTACT(S):
Public Works
Aaron Bert
425-556-2786

DEPARTMENT STAFF:
Public Works
Aaron Noble
Project Manager
Planning and Community Development
Micah Ross
Senior Engineer
Public Works
Steve Gibbs
Capital Projects Division Manager
Public Works
Vangie Garcia
Deputy Public Works Director


TITLE:
title
Award Construction Contract to A1 Landscaping of Snohomish, WA, in the Amount of $2,739,391, for the Bel-Red Buffered Bike Lanes Project


OVERVIEW STATEMENT:
recommendation
??Public Works is requesting to award the construction contract for the Bel-Red Buffered Bike Lanes Project, Project No. 2329, to A1 Landscaping in the amount of $2,739,391.

This project will add buffered bike lanes along Bel-Red Road from NE 30th St to West Lake Sammamish Parkway. This project will also make 22 curb ramps ADA compliant, replace the sidewalk, overlay the roadway, and make improvements to the traffic signals.
body

? Additional Background Information/Description of Proposal Attached


REQUESTED ACTION:

? Receive Information ? Provide Direction ? Approve


REQUEST RATIONALE:

* Relevant Plans/Policies:
Transportation Master Plan
* Required:
Council approval is required to award a Public Works contract that exceeds $300,000 (2018 City Resolution 1503).
* Council Request:
N/A
* Other Key Facts:
Public Works is requesting this item go forward for Council approval at the July 15, 2025, Council business meeting.


OUTCOMES:
Improved pedestrian and bicycle access to Overlake Village, the Microsoft Campus and Light Rail. If approved, construction will begin before August and paving will be completed this year.



COMMUNITY/STAKEHOLDER OUTREACH AND INVOLVEMENT:

* Timeline (previous or planned):
- September 2024 - Door Hangers
- February 2025 - Mailers were delivered
- July 2025 - Traffic Alerts and project signs
- Email newsletter and social media to alert commuters will be timed to approximate...